Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (plastic) 12 sq ft. $ 0.72 per sq. ft. $8.64 Direct labor 0.25 hr. $ 12.20 per hr. 3.05 Variable manufacturing overhead (based on direct labor hours) 0.25 hr. $ 1.20 per hr. 0.30 Fixed manufacturing overhead ($378,000 ÷ 900,000 units) 0.42 Parker Plastic had the following actual results for the past year: Number of units produced and sold 1,000,000 Number of square feet of plastic used 11,800,000 Cost of plastic purchased and used $ 8,260,000 Number of labor hours worked 245,000 Direct labor cost $ 2,891,000 Variable overhead cost $ 318,500 Fixed overhead cost $ 355,000 Required: Calculate Parker Plastic’s direct materials price and quantity variances. (Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
Material price variance = (Standard price-actual price)actual quantity purchased = (0.72*11800000-8260000) = 236000 F
Material quantity variance = (Standard qty-actual qty)Standard price = (1000000*12-11800000)0.72 = 144000 F
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information...
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard Quantity 12 sq ft. 0.25 hr. Standard Price (Rate) Standard Unit Cost $ 0.72 per sq. ft. $8.64 $12.20 per hr. 3.05 Direct materials (plastic) Direct labor Variable manufacturing overhead (based on direct labor hours) Fixed manufacturing overhead ($378,000 + 900,000 units) 0.25 hr. $ 1.20 per hr. 0.39 0.42 Parker Plastic had the following actual results for the...
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard Standard Price (Rate) init Cost Standard Quantity 12 sq ft. 8.25 hr. $ 0.72 per sq. ft. $12.20 per hr. 58.64 3.es Direct materials (plastic) Direct labor Variable manufacturing overhead (based on direct labor hours) Fixed manufacturing overhead ($378,000 + 900,000 units) 0.25 hr. $ 1.20 per hr. 0.30 0.42 Parker Plastic had the following actual results for the...
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (plastic) 12 sq ft. $ 1.00 per sq. ft. $ 12.00 Direct labor 0.25 hr. $ 12.80 per hr. 3.20 Variable manufacturing overhead (based on direct labor hours) 0.25 hr. $ 2.00 per hr. 0.50 Fixed manufacturing overhead $559,200 ÷ 932,000 units) 0.60 Parker Plastic had the following actual results...
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (plastic) 12 sq ft. $ 0.83 per sq. ft. $ 9.96 Direct labor 0.25 hr. $ 10.50 per hr. 2.62 Variable manufacturing overhead (based on direct labor hours) 0.25 hr. $ 2.20 per hr. 0.55 Fixed manufacturing overhead $345,800 ÷ 910,000 units) 0.38 Parker Plastic had the following actual results...
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (plastic) 8 sq ft. $ 0.63 per sq. ft. $ 5.04 Direct labor 0.26 hr. $ 10.50 per hr. 2.73 Variable manufacturing overhead (based on direct labor hours) 0.26 hr. $ 1.50 per hr. 0.39 Fixed manufacturing overhead $308,040 ÷ 906,000 units) 0.34 Parker Plastic had the following actual results...
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (plastic) 10 sq ft. $ 0.82 per sq. ft. $ 8.20 Direct labor 0.25 hr. $ 10.20 per hr. 2.55 Variable manufacturing overhead (based on direct labor hours) 0.25 hr. $ 1.40 per hr. 0.35 Fixed manufacturing overhead $270,600 ÷ 902,000 units) 0.30 Parker Plastic had the following actual results...
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (plastic) 8 sq ft. $ 0.63 per sq. ft. $ 5.04 Direct labor 0.26 hr. $ 10.50 per hr. 2.73 Variable manufacturing overhead (based on direct labor hours) 0.26 hr. $ 1.50 per hr. 0.39 Fixed manufacturing overhead $308,040 ÷ 906,000 units) 0.34 Parker Plastic had the following actual results...
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (plastic) 11 sq ft. $ 1.26 per sq. ft. $ 13.86 Direct labor 0.3 hr. $ 11.70 per hr. 3.51 Variable manufacturing overhead (based on direct labor hours) 0.3 hr. $ 2.10 per hr. 0.63 Fixed manufacturing overhead $441,600 ÷ 920,000 units) 0.48 Parker Plastic had the following actual results...
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Direct materials (plastic) Direct labor Variable manufacturing overhead (based on direct labor hours) Fixed manufacturing overhead $500,040 - 926,000 units) Standard Quantity 13 sq ft 0.25 hr. 0.25 hr. Standard Price (Rate) S 0.70 per sq. ft. S 12.20 per hr. $ 1.40 per hr. Standard Unit Cost S 9.10 3.05 0.35 0.54 Parker Plastic had the following actual results...
Parker Plastic, Inc., manufactures plastic mats to use with rolling office chairs. Its standard cost information for last year follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (plastic) 8 sq ft. $ 1.02 per sq. ft. $ 8.16 Direct labor 0.3 hr. $ 11.10 per hr. 3.33 Variable manufacturing overhead (based on direct labor hours) 0.3 hr. $ 2.60 per hr. 0.78 Fixed manufacturing overhead $383,880 ÷ 914,000 units) 0.42 Parker Plastic had the following actual results...