Data for six weeks from a carpeting crew is as follows:
Week | Crew Size | Yards Installed |
1 | 4 | 96 |
2 | 3 | 72 |
3 | 4 | 92 |
4 | 2 | 50 |
5 | 3 | 69 |
6 | 2 | 52 |
Compute the labor productivity (= yards installed per crew member) for each of the six weeks. Which week has the highest productivity?
Answer 1:
Labor productivity (= yards installed per crew member) is computed for each of the six weeks as below:
Answer 2:
From the answer above, we observe that highest productivity is 26 Yards installed per crew member which occurs in week 6.
Week 6 has highest productivity.
Data for six weeks from a carpeting crew is as follows: Week Crew Size Yards Installed...
1. A catering company prepared and served 300 meals at an anniversary celebration last week using eight workers. The week before, six workers prepared and served 240 meals at a wedding reception. a. For which event was the labor productivity higher? Explain. b. What are some possible reasons for the productivity differences? 2. The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining these figures: Week Crew Size Yards Installed 4...
The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining these figures: Week Yards Installed 100 75 105 55 a. Compute the labor productivity for each of the weeks. (Round your answers to 2 decimal places.) Labor productivity (Yards/Person) Week rew size b. Which crew size works best? A crew of seems to work best.
2. The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining these figures: Week Crew Size Yards Installed به لبه NW NA Wt ه ه ی Compute the labor productivity for each of the weeks. On the basis of your calculations, what can you conclude about crew size and productivity?
Chapter 2 Homework Help Save & Exit Su Problem 2-2 The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining these figures: points Crew Size Yards Installed 102 eloos References a. Compute the labor productivity for each of the weeks. (Round your answers to 2 decimal places.) Week Labor productivity (Yards/Person) Crew size b. Which crew size works best? A crew of seems to work best.
Perform a multi-factor analysis for each week using both input factors together (labor & materials) Perform a single factor productivity analysis for each week using each of the two inputs separately (labor & materials) DATA: Input Week Output Labor Amt Matls # 1 96 4 60.0 2 72 3 50.0 3 92 4 100.0 4 50 2 40.0 5 69 3 60.0 6 52 2 50.0 Materials = $50.00 per pound (#) Labor = 8 hours/day @ 5 days/wk...
How many days would it take a crew to install 13,600 LF of base molding if they work five, eight-hour days per week and are able to install 100 LF of base molding per hour? How many days would it take a crew to install 13,600 LF of base molding if they work eleven-hour days, six days per week if their hourly productivity rate is 100 LF when not working overtime? Table 1: Production Efficiency Table for Use in Questions...
Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $14. Overhead is 1.5 times weekly labor cost. Material cost is $8 per pound. (Round your answers to 2 decimal places.) Week Output (units) Workers Material (lbs) 1 29,000 4 470 2 34,000 7 540 3 30,000 7 490 4 35,000 9 530
Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) ] Week Output (units) Workers Material (lbs) 1: 28,000 7 430 2: 33,000 8 480 3: 32,000 4 520 4: 42,000 9 620
QUESTION 18 Questions 15-18) The following table shows data on the average number of chocolate bars produced each week, together with data for labor and material Assume 40-hour weeks and an hourly wage of $15 Overhead is 1.5 times weekly labor cost Material cost is $10 per pound #Chocolate bars Produced / Weekl#Workers Material (lbs Week 1 Week 2 40,000 45,000 6 510 530 Compute the productivity growth from Week 1 to Week 2 using the multifactor productivities. Round the...
The Langosta Company reported data for 1997 and 1998 as follows: 1997 1998 The number of machines produced 60.000 75.000 Labor hours 20.000 18.750 The material used (kg) 600.000 850.000 Selling price per unit (machine) $50 $45 Hourly labor costs $10 $10 Material cost per kg $2 $4 REQUESTED: 1. Calculate productivity profiles in 1997 and 1998. Are there productivity improvements? 2. Calculate productivity measures related to earnings for 1998. Are there productivity improvements?