Question

Your company estimates that the flotation cost to finance a project is 5 percent. When evaluating...

Your company estimates that the flotation cost to finance a project is 5 percent. When evaluating the project's NPV, you should:

add 5 percent to the firm's WACC to get the discount rate for the project.

increase the project's discount by multiplying the firm's WACC by 1.05.

increase the project's discount rate by dividing the firm's WACC by (1 - 0.05).

multiply the project's start-up cost by 1.05.

divide the project's start-up cost by 0.95.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Correct answer is:

divide the project's start-up cost by 0.95.

Explanation:

Flotation cost to finance a project is 5 percent

When evaluating the project's NPV we need initial investment.

Start up cost = Initial Investment - Flotation cost = Initial investment * (1 - 5%)

=> Initial Investment = Start up cost / (1 - 5%) = Start up cost / 0.95

Hence option E is correct and other options A, B, C and D are incorrect.

Add a comment
Know the answer?
Add Answer to:
Your company estimates that the flotation cost to finance a project is 5 percent. When evaluating...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT