Question

Part 2 Remember the old saying, “A project plan is not a schedule until resources are...

Part 2 Remember the old saying, “A project plan is not a schedule until resources are committed.” This exercise illustrates this sometime subtle, but important point. Using your files from Part 1, input resources and their costs if you have not already done so. All information is found in Tables A2.1 and A2.2. Prepare a memo that addresses the following questions: 1. Which if any of the resources are overallocated? 2. Assume that the project is time constrained and try to resolve any overallocation problems by leveling within slack. What happens? 3. What is the impact of leveling within slack on the sensitivity of the network?Page 619 Include a Gantt chart with the schedule table after leveling within slack. 4. Assume the project is resource constrained and resolve any overallocation problems by leveling outside of slack. What happens? Include a Gantt chart with the schedule table after leveling outside of slack. Note: No splitting of activities is allowed. Note: No partial assignments (e.g., 50 percent). All resources must be assigned 100 percent.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1).

ANS- Four of the resources are over allocated, marketing, design, industrial, and purchasing.

2).

ANS- When leveling within slack, we clear up most problems. However, Development is still overallocated for most of its time, as noted above.

3).

ANS- Leveling within slack can affect the network greatly. After you level within slack some over

allocated resources can now be allocated. Like resource-constrained schedules, leveling caused

complexity to be increased because the resource constrains are added to the technical constrains

and the critical path can be affect because of leveling within slack. Leveling with slack would

increase the chances that a different critical path with occur because slack can play a huge role

on schedules.

Explanation:

Add a comment
Know the answer?
Add Answer to:
Part 2 Remember the old saying, “A project plan is not a schedule until resources are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You have prepared the following schedule for a project in which the key resource is a...

    You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having four backhoes. You receive a call from your partner, Brooker, who desperately needs one of your backhoes. You tell Brooker you are willing to let him have the backhoe if you are still able to complete your project in 13 months. Develop a resource schedule to see if it is possible to complete the project in 13...

  • Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project...

    Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft Excel to complete this item and include all calculations in your Excel file. Note that showing all calculations in Excel is required. 2. Complete Appendix Exercise 2 at end of Chapter 13 in Larson and Gray. Specifically, complete the table on pp. 509-510 in the textbook (note th...

  • Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the...

    Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the Green Computing Research Project. The company’s CIO, Ben, is the project sponsor, and Ito is the program manager for the larger Environmental Technologies Program that this project is part of. Now you need to put together your project team and get to work on this high-visibility project. You will work with Ben to handpick your team. Ben had already worked with the HR department...

  • Performance Improvement programs and effective project management require an understanding of the four phases of the...

    Performance Improvement programs and effective project management require an understanding of the four phases of the project life-cycle: initiation, planning, execution/implementation, and closure. It is important to have each phase of the project mapped on a timeline and to be sure the project team has the appropriate members with the right skills to ensure a successful program. Using a case study from the text, students will demonstrate their ability to review and evaluate a performance improvement program by arranging the...

  • Please read through the article below and answer the question at the end of the article....

    Please read through the article below and answer the question at the end of the article. What Are the Project Management Knowledge Areas? PMI created a set of standard terminology and guidelines for project management, which is known as the project management knowledge areas. This is an evolving standard that is updated periodically in its PMBOK. Project management knowledge areas coincide with the process groups, which are project initiation, project planning, project execution, monitoring and controlling, and project closing. These...

  • QUESTION 1: Why must project manager should have good technical skills but also good management skills?...

    QUESTION 1: Why must project manager should have good technical skills but also good management skills? QUESTION 2: **Communication and Communicator are related" This quote from the text suppose that the communication process is lead by the spokeperson. Do you think is it a gift" to be a good communicator or a skill to improve ( use example of your knowledge to answer)? QUESTION 3: Look at the text paragraph yellow highlighted, and do you think that in today's world...

  • Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241...

    Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241 through 246). Question 2 Prepare a plan for the remainder of the project in response to Adams’ memo (lines 241 through 246). Your answers to the above will be assessed in terms of the level of communication displayed, the insights and inferences drawn, and your ability to...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • Please read the article and answer about questions. You and the Law Business and law are...

    Please read the article and answer about questions. You and the Law Business and law are inseparable. For B-Money, the two predictably merged when he was negotiat- ing a deal for his tracks. At other times, the merger is unpredictable, like when your business faces an unexpected auto accident, product recall, or government regulation change. In either type of situation, when business owners know the law, they can better protect themselves and sometimes even avoid the problems completely. This chapter...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT