You are choosing between two projects. The cash flows for the projects are given in the following table ($ million):
Project |
Year 0 |
Year 1 |
Year 2 |
Year 3 |
Year 4 |
A |
−$49 |
$25 |
$19 |
$22 |
$14 |
B |
$99 |
$21 |
$42 |
$51 |
$61 |
a. What are the IRRs of the two projects? b. If your discount rate is 5.1%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently?
Project | A | ||||||||
Year | Cashflow | PV @ 10% | Amount | PV @ 20% | Amount | ||||
0 | -49 | 1 | -49 | 1 | -49 | ||||
1 | 25 | 0.91 | 22.73 | 0.83 | 20.83 | ||||
2 | 19 | 0.83 | 15.70 | 0.69 | 13.19 | ||||
3 | 22 | 0.75 | 16.53 | 0.58 | 12.73 | ||||
4 | 14 | 0.68 | 9.56 | 0.48 | 6.75 | ||||
15.52 | 4.51 | ||||||||
By interpolation formula | |||||||||
IRR = | 10+(15.52/(15.52-4.51)*(20-10)) | ||||||||
24.09628 | |||||||||
24.10% | |||||||||
Project | B | ||||||||
Year | Cashflow | PV @ 10% | Amount | PV @ 20% | Amount | ||||
0 | -99 | 1 | -99 | 1 | -99 | ||||
1 | 21 | 0.91 | 19.09 | 0.83 | 17.50 | ||||
2 | 42 | 0.83 | 34.71 | 0.69 | 29.17 | ||||
3 | 51 | 0.75 | 38.32 | 0.58 | 29.51 | ||||
4 | 61 | 0.68 | 41.66 | 0.48 | 29.42 | ||||
34.78 | 6.60 | ||||||||
By interpolation formula | |||||||||
IRR = | 10+(34.78/(34.78-6.60)*(20-10)) | ||||||||
22.34209 | |||||||||
22.34% | |||||||||
Assuming $99 as outflow of cash, therefore showing in negative. As such is required | |||||||||
for the correct answer. | |||||||||
Project | A | Project | B | ||||||
Year | Cashflow | PV @ 5.1% | Amount | Year | Cashflow | PV @ 5.1% | Amount | ||
0 | -49 | 1 | -49 | 0 | -99 | 1 | -99 | ||
1 | 25 | 0.95 | 23.79 | 1 | 21 | 0.95 | 19.98 | ||
2 | 19 | 0.91 | 17.20 | 2 | 42 | 0.91 | 38.02 | ||
3 | 22 | 0.86 | 18.95 | 3 | 51 | 0.86 | 43.93 | ||
4 | 14 | 0.82 | 11.47 | 4 | 61 | 0.82 | 49.99 | ||
NPV | 22.41 | NPV | 52.93 | ||||||
As per IRR project A is acceptable but as per NPV project B | |||||||||
IRR and NPV rank the project differently because IRR will rank the project showing higher investment | |||||||||
return regardless of total value added whereas NPV rank the project adding more value higher | |||||||||
regardless of the initial investment required. | |||||||||
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A negative $ 51 $ 25 $ 22 $ 21 $ 13 B negative $ 99 $ 22 $ 42 $ 50 $ 59 a. What are the IRRs of the two projects? b. If your discount rate is 5.1 %, what are the NPVs of the two projects?...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 - $49 - $101 Year 1 $26 $18 Year 2 $19 $42 Year 3 $21 $52 Year 4 $17 $61 a. What are the IRRs of the two projects? b. If your discount rate is 5.2%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 - $50 $18 $19 $17 - $101 $21 $40 $51 $26 $59 a. What are the IRRs of the two projects? b. If your discount rate is 5.1%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the following table (S million): Project A Year 0 Year 1 Year 2 Year 3 Year 4 $25 $22 -$49 -$98 $19 $48 $17 $60 B $20 $42 a. What are the IRRS of the two projects? b. If your discount rate is 4.6%, what are the NPVS of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 - $49 - $98 Year 1 $26 $20 Year 2 $20 $39 Year 3 $19 $49 Year 4 $16 $61 a. What are the IRRs of the two projects? b. If your discount rate is 4.7%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A negative $ 49−$49 $ 27$27 $ 19$19 $ 19$19 $ 17$17 B negative $ 101−$101 $ 21$21 $ 42$42 $ 48$48 $ 62$62 a. What are the IRRs of the two projects? b. If your discount rate is 4.9%, what are the NPVs of the two projects? c....
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 1 Year 2 Year 0 - $51 - $102 $26 $20 Year 3 $20 $49 Year 4 $12 $58 $21 $38 a. What are the IRRs of the two projects? b. If your discount rate is 4.7%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the following table (s million) Project Year 1 Year 3 Year 0 -$50 - $99 Year 2 $20 $25 $18 Year 4 $16 $19 $442 $49 a. What are the IRRs of the two projects? b. If your discount rate is 53% what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 -$52 $26 $22 - $102 $20 $41 Year 4 Year 3 $21 $49 $14 $58 a. What are the IRRs of the two projects? b. If your discount rate is 5.5%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$48 $ 26 $ 18 $22 $ 13 B −$102 $ 20 $ 42 $50 $61 a. What are the IRRs of the two projects? b. If your discount rate is 4.7 % 4.7%, what are the NPVs of the two projects? c. Why do IRR and NPV...