Question

You are choosing between two projects. The cash flows for the projects are given in the...

You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million):

Project

Year 0

Year 1

Year 2

Year 3

Year 4

A

−$49

$25

$19

$22

$14

B

$99

$21

$42

$51

$61

a. What are the IRRs of the two​ projects? b. If your discount rate is 5.1%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Project A
Year Cashflow PV @ 10% Amount PV @ 20% Amount
0 -49 1 -49 1 -49
1 25 0.91 22.73 0.83 20.83
2 19 0.83 15.70 0.69 13.19
3 22 0.75 16.53 0.58 12.73
4 14 0.68 9.56 0.48 6.75
15.52 4.51
By interpolation formula
IRR         = 10+(15.52/(15.52-4.51)*(20-10))
24.09628
24.10%
Project B
Year Cashflow PV @ 10% Amount PV @ 20% Amount
0 -99 1 -99 1 -99
1 21 0.91 19.09 0.83 17.50
2 42 0.83 34.71 0.69 29.17
3 51 0.75 38.32 0.58 29.51
4 61 0.68 41.66 0.48 29.42
34.78 6.60
By interpolation formula
IRR         = 10+(34.78/(34.78-6.60)*(20-10))
22.34209
22.34%
Assuming $99 as outflow of cash, therefore showing in negative. As such is required
for the correct answer.
Project A Project B
Year Cashflow PV @ 5.1% Amount Year Cashflow PV @ 5.1% Amount
0 -49 1 -49 0 -99 1 -99
1 25 0.95 23.79 1 21 0.95 19.98
2 19 0.91 17.20 2 42 0.91 38.02
3 22 0.86 18.95 3 51 0.86 43.93
4 14 0.82 11.47 4 61 0.82 49.99
NPV 22.41 NPV 52.93
As per IRR project A is acceptable but as per NPV project B
IRR and NPV rank the project differently because IRR will rank the project showing higher investment
return regardless of total value added whereas NPV rank the project adding more value higher
regardless of the initial investment required.
Add a comment
Know the answer?
Add Answer to:
You are choosing between two projects. The cash flows for the projects are given in the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A negative $ 51 $ 25 $ 22 $ 21 $ 13 B negative $ 99 $ 22 $ 42 $ 50 $ 59 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.1 %​, what are the NPVs of the two​ projects?...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 - $49 - $101 Year 1 $26 $18 Year 2 $19 $42 Year 3 $21 $52 Year 4 $17 $61 a. What are the IRRs of the two projects? b. If your discount rate is 5.2%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 - $50 $18 $19 $17 - $101 $21 $40 $51 $26 $59 a. What are the IRRs of the two projects? b. If your discount rate is 5.1%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table (S million): Project A Year 0 Year 1 Year 2 Year 3 Year 4 $25 $22 -$49 -$98 $19 $48 $17 $60 B $20 $42 a. What are the IRRS of the two projects? b. If your discount rate is 4.6%, what are the NPVS of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 - $49 - $98 Year 1 $26 $20 Year 2 $20 $39 Year 3 $19 $49 Year 4 $16 $61 a. What are the IRRs of the two projects? b. If your discount rate is 4.7%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A negative $ 49−$49 $ 27$27 $ 19$19 $ 19$19 $ 17$17 B negative $ 101−$101 $ 21$21 $ 42$42 $ 48$48 $ 62$62 a. What are the IRRs of the two​ projects? b. If your discount rate is 4.9%​, what are the NPVs of the two​ projects? c....

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 1 Year 2 Year 0 - $51 - $102 $26 $20 Year 3 $20 $49 Year 4 $12 $58 $21 $38 a. What are the IRRs of the two projects? b. If your discount rate is 4.7%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table (s million) Project Year 1 Year 3 Year 0 -$50 - $99 Year 2 $20 $25 $18 Year 4 $16 $19 $442 $49 a. What are the IRRs of the two projects? b. If your discount rate is 53% what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 -$52 $26 $22 - $102 $20 $41 Year 4 Year 3 $21 $49 $14 $58 a. What are the IRRs of the two projects? b. If your discount rate is 5.5%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$48 $ 26 $ 18 $22 $ 13 B −$102 $ 20 $ 42 $50 $61 a. What are the IRRs of the two​ projects? b. If your discount rate is 4.7 % 4.7%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT