Asper Corporation has provided the following data for February. Denominator level of activity 9,700 machine-hours Budgeted...

Asper Corporation has provided the following data for February. Denominator level of activity 9,700 machine-hours Budgeted fixed manufacturing overhead costs $ 288,420 Fixed component of the predetermined overhead rate $ 36.60 per machine-hour Actual level of activity 9,900 machine-hours Standard machine-hours allowed for the actual output 10,200 machine-hours Actual fixed manufacturing overhead costs $ 279,960 The budget variance for February is:

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Fixed Budget Variance

Budgeted Fixed Manufacturing Overheads

$288,420

Fixed Overhead Cost Applied (Refer Note)

$288,456

Fixed Overhead Volume Variance

$ 36

Favorable

Note:

Std machine hours allowed for the actual output

10,200

MHs

Std Fixed Overhead Rate per machine hour

($288,420 / Denominator level of activity 10,200 MHs)

$28.28(approximately)

Per MH

Applied Fixed Overhead Cost

$288,456

Add a comment
Know the answer?
Add Answer to:
Asper Corporation has provided the following data for February. Denominator level of activity 9,700 machine-hours Budgeted...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT