Question

Which one of these statements is correct concerning the time value of money? Decreasing the PV...

Which one of these statements is correct concerning the time value of money?

Decreasing the PV decreases the FV.

Increasing the initial cost of a project increases the project's NPV

Increasing the discount rate, increases the PV of a project.

Increasing the FV decreases the PV

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer is Decreasing the PV decreases the FV.

Explanation: The higher the present value, higher will be the future value of such amount. Thus, if the present value decreases, the future value of such amount will get increased.

Add a comment
Know the answer?
Add Answer to:
Which one of these statements is correct concerning the time value of money? Decreasing the PV...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • which one of the following statements is correct concerning net present value or NPV? please explain...

    which one of the following statements is correct concerning net present value or NPV? please explain why a) if cash flow of a project at time 0 is increased ny $100, the NPV of the project will increase by $100 b)the timing of the cash inflows has no effect on NPV of projrct c) if cash inflows of a project can be received sooner, NPV of project will increase d) if project has negative NPV at 9% discount rate, it...

  • Question 30 (1 point) Which of the following statements is CORRECT? Assume that the project being...

    Question 30 (1 point) Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. A project's regular IRR is found by compounding the initial cost at the WACC to find the terminal value (TV), then discounting the TV at the WACC. A project's regular IRR is found by compounding the cash inflows at the WACC to find the present value (PV), then discounting the...

  • Which of the following statements is CORRECT? Assume that the project being considered has normal cash...

    Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. A project's regular IRR is found by compounding the cash inflows at the cost of capital to find the terminal value (TV), then discounting this TV at the cost of capital. b. To find a project's IRR, we must find a discount rate that is equal to the cost of capital. c. If...

  • Which of the following statements is CORRECT? Assume that the project being considered has normal cash...

    Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Group of answer choices A) If a project's IRR is positive, then its NPV must also be positive. B) A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost. C) If a project's IRR is smaller than the WACC, then its NPV will be positive....

  • Which of the following statements is CORRECT? Assume that the project being considered has normal cash...

    Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. A project's regular IRR is found by compounding the cash inflows at the WACC to find the terminal value (TV), then discounting this TV at the WACC. b. A project's regular IRR is found by discounting the cash inflows at the WACC to find the present value (PV), then compounding this PV to...

  • Which of the following statements is CORRECT? Assume that the project being considered has normal cash...

    Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one cash outflow at t = o followed by a series of positive cash flows. 10 a. If a project's IRR is greater than its WACC, then its MIRR will be greater than the IRR. b. To find a project's MIRR, we compound cash inflows at the regular IRR and then find the discount rate that causes the PV of the terminal...

  • Which one of the following statements correctly defines a time value of money relationship? Multiple Choice...

    Which one of the following statements correctly defines a time value of money relationship? Multiple Choice 2.5 points eBook • Time and future values are inversely related, all else held constant. Print References O Interest rates and time are positively related, all else held constant. O An increase in a positive discount rate increases the present value. O An increase in time increases the future value given a zero rate of interest. O Time and present value are inversely related,...

  • Which ofthe following statements is true regarding net present value? A. NPV decreases as the required...

    Which ofthe following statements is true regarding net present value? A. NPV decreases as the required return on the project increases B. NPV decreases as the discount rate decreases C. NPV is unaffected by the timing of the project’s cash flows. D. NPV is equal to the initial investment when the required return is equal to the IRR

  • 8. Which of the following statementele mele wing statements is correct for a project with a...

    8. Which of the following statementele mele wing statements is correct for a project with a positive NPV? A) IRR exceeds the cost of capital B) Accepting the project has an indeterminate effect on shareholders C) The discount rate exceeds the cost of capital. D) The profitability index equals one. 9. If the net present value of a project which costs $20,000 is $5,000 when the discount rate is 10%, then the: A) project's IRR equals 10%. B) project's rate...

  • Which of the following statements is correct? A project's discounted payback period (DBP) is normally shorter...

    Which of the following statements is correct? A project's discounted payback period (DBP) is normally shorter than its traditional payback period (PB) because DPB accounts for the time value of money, whereas PB does not. To compute the NPV for a project, the firm's required rate of return must be known. To compute a project's internal rate of return (IRR), the firm's required rate of return is not used because the IRR is the discount rate where the project's NPV...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT