Question

Question :1 (40%, 8% per sub question) A firm is evaluating two mutually exclusive projects that...

Question :1 (40%, 8% per sub question)
A firm is evaluating two mutually exclusive projects that have unequal lives. The firm must evaluate the projects using the annualized net present value approach and recommend which project they should select. The firm's cost of capital has been determined to be 14 percent, and the projects have the following initial investments and cash flows:

  1. The NPVs of Projects R and S are

  2. The annualized NPV of Project R is

  3. The annualized NPV of Project S is

  4. Which project should be chosen on the basis of the normal NPV approach?

  5. Which project should be chosen using the Annualized NPV approach?

PROJECT R PROJECT S

INITIAL INVESTMENT 40,000 58,000

CASH FLOW. 1. 20,000 30,000

2. 20,000 55,000

3. 20,000

4. 20,000

PLEASE SHOW WORK FOR EACH QUESTION THANKS!!

0 0
Add a comment Improve this question Transcribed image text
Answer #1
  1. The NPVs of Projects R and S are 18274.25 and 10636.50

  2. The annualized NPV of Project R is 6271.81

  3. The annualized NPV of Project S is 6459.44

  4. Which project should be chosen on the basis of the normal NPV approach? Project R (Higher NPV)

  5. Which project should be chosen using the Annualized NPV approach? Project S (Higher NPV)

Year R S
0 -40000 -58000
1 20000 30000
2 20000 55000
3 20000
4 20000
NPV 18274.25 10636.50
Annualized NPV $6,271.81 $6,459.44

Add a comment
Know the answer?
Add Answer to:
Question :1 (40%, 8% per sub question) A firm is evaluating two mutually exclusive projects that...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Part Two: Problems (60%): Write down your answers in the following two answer sheets. You have...

    Part Two: Problems (60%): Write down your answers in the following two answer sheets. You have to show me your work to get credits. Question :1 (40%, 8% per sub question) A firm is evaluating two mutually exclusive projects that have unequal lives. The firm must evaluate the projects using the annualized net present value approach and recommend which project they should select. The firm's cost of capital has been determined to be 14 percent, and the projects have the...

  • (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive...

    (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project A Project B Cash Flow Cash Flow $(102,000) $(102,000) 40,000 40.000 40.000 40,000 0 40,000 215,000 If the appropriate discount rate on these projects is 9 percent, which would be chosen and why? The NPV of Project Ass (Round to the nearest cont.)

  •    Yong Importers, an Asian import company, is evaluating two mutually exclusive projects, A and B. The...

       Yong Importers, an Asian import company, is evaluating two mutually exclusive projects, A and B. The relevant cash flows for each project are given in the table below. The cost of capital for use in evaluating each of these equally risky projects is 10 percent. initial investment               project a                   project b                                            $350,000                  $425,000 year                                              cash inflows (cf) 1                                         140,000                  175,000 2                                         165,000                   150,000 3                                          190,000                  125,000 4                                                                         100,000 5                                                                         75,000 6                                                                         50,000 Which project should be chosen on the basis of...

  • Thomas Company is considering two mutually exclusive projects. The firm has a 12% cost of capital....

    Thomas Company is considering two mutually exclusive projects. The firm has a 12% cost of capital. Cash inflows Initial investment Year 1 Year 2 Year 3 Year 4 Year 5 Project A Project B $130000 $85000 $25000 $35000 $45000 $50000 $55000 $40000 $35000 $30000 $10000 $5000 Evaluate and discuss the rankings of NPV and IRR of the two projects on the basis of your finding. O A Project B should be chosen because it has a higher IRR than Project...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Assuming the projects are independent, which one(s) would you recommend? -Select-Only Project M would be accepted because NPV(M) > NPV(N).Only Project N would be accepted because NPV(N) > NPV(M).Both projects would be accepted since both...

  • , A firm is evaluating the following two mutually exclusive, but quite profitable 2-year projects...

    , A firm is evaluating the following two mutually exclusive, but quite profitable 2-year projects I and II, with cash flows at t0,1 and 2 as follows: Year t Project I Project II - $10,000 +20,000 +10,000 $10,000 +$40,000 Compute each project's NPV for r=0% and r=10%, where r= discount rate or required rate Based on the cash flow patterns for the two projects and the answer to part a), can we Using the analytical formulation of the intersection of...

  • 6) A firm is evaluating three mutually exclusive capital budgeting projects. The net present value of...

    6) A firm is evaluating three mutually exclusive capital budgeting projects. The net present value of each project is shown below. Given this information, which project() should the firm accept? Project 1 100,000 NPV, S Project 2 10,000 Project 3 - 100,000 a) accept Projects 1 and 2, and reject Project 3 b) accept Projects 1 and 3, and reject Project 2 c) accept Project 3, and reject Projects 1 and 2 d) accept Project 1, and reject Projects 2...

  • CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...

    CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...

  • CAPITAL BUDGETING CRITERIA 1. A firm with a 13% WACC is evaluating two projects for this...

    CAPITAL BUDGETING CRITERIA 1. A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to...

  • You are trying to determine which of two none mutually exclusive projects to undertake. Project A...

    You are trying to determine which of two none mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 1 1.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1 0 3.50 The cost of capital for both projects is 9%, and the prolects have different lives. If the projects are not repeatable,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT