4.9 An automotive powertrain system consists of engine, transmission, and axle subsystems connected in logic series. The reli

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Since the subsystem are connected in a series connection therefore the failure of one component lead to the failure of whole assembly.

In this case the product of reliability of all the three components is in turn equal to the total reliability of the assembly.

Q1

Given

Total reliability of the assembly = .98

we get

assembli

where R1,R2 and R3 are the individual reliabilities of the subsystems.

Given equal reliability allocation for each subsystem or component,

i.e.R1 = = = Y R2 R3

We have r^3= R = .98

Therefore r = .99328

.....................................................................................

Q2

Here failures per month are given for each component.

Since the reliability follows exponential function. i.e.

R= e^{-\lambda t}

Where

λ = failure rate of th subsystem

λ1-6.3 * 10

Corresponding reliability

operating time 36 months (given)

Therefore answer is-

R1 =  e^{-{\lambda_1}*t} = 0.9977346

R2 =  e^{-{\lambda_2}*t} = 0.9988

R3 = e^{-{\lambda_3}*t} = 0.9991723.

Add a comment
Know the answer?
Add Answer to:
4.9 An automotive powertrain system consists of engine, transmission, and axle subsystems connect...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4.9 An automotive powertrain system consists of engine, transmission, and axle subsystems connect...

    4.9 An automotive powertrain system consists of engine, transmission, and axle subsystems connected in logic series. The reliability target of the powertrain system is 0.98 at 36 months. Allocate the reliability target equally to each subsystem. 4.9 An automotive powertrain system consists of engine, transmission, and axle subsystems connected in logic series. The reliability target of the powertrain system is 0.98 at 36 months. Allocate the reliability target equally to each subsystem.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT