4. Your company has been asked to develop a conveyor belt system which packages six bottles into ...
5. You have been asked to develop a system to mix and bottle orange juice from concentrate. (5 points) HINT: Select a PLC with 6 outputs. a. Low level detectors in the water 1) and concentrate (12) tanks prevent operating the water (Q1) and concentrate (Q2) pumps. b. The orange juice tank has a high level detector (14) which stops the pumps in the water and concentrate tanks. c. The conveyor belt motor (Q4) is initiated by a start (16)...
You have been asked to develop a system to mix and bottle orange juice from concentrate. a. Low level detectors in the water (I1) and concentrate (I2) tanks prevent operating the water (Q1) and concentrate (Q2) pumps. b. The orange juice tank has a high level detector (I4) which stops the pumps in the water and concentrate tanks. c. The conveyor belt motor (Q4) is initiated by a start (I6) and stop (I7) button. d. When a bottle is detected...