Question

Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factorie...

Factory Overhead Rates, Entries, and Account Balance

Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows:

Factory 1 Factory 2
Estimated factory overhead cost for fiscal
year beginning March 1 $1,018,350 $889,600
Estimated direct labor hours for year 13,900
Estimated machine hours for year 22,630
Actual factory overhead costs for March $81,640 $76,800
Actual direct labor hours for March 1,250
Actual machine hours for March 1,770

a. Determine the factory overhead rate for Factory 1.
$ per machine hour

b. Determine the factory overhead rate for Factory 2.
$ per direct labor hour

Feedback

a-b. Factory 1 overhead is applied based on machine hours. Factory 2 overhead is applied based on direct labor hours.

c. Journalize the entries to apply factory overhead to production in each factory for March.

Factory 1 Work in Process
Factory Overhead
Factory 2 Work in Process
Factory Overhead

Feedback

c. Increase the work in process and reduce the factory overhead.

d. Determine the balances of the factory overhead accounts for each factory as of March 31, and indicate whether the amounts represent overapplied factory overhead or underapplied factory overhead.

Factory 1 $ Debit Underapplied
Factory 2 $ Credit Overapplied
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) Factory overhead rate for Factory 1 = $1,018,350/22630 = $45 per hour

b) Factory overhead rate for Factory 2 = $889,600/13900 = $64 per hour

c) Journal entries for the two factories will be

General Journal Debit Credit
Factory 1 Work in Process 79650
Factory Overhead 79650
Factory 2 Work in Process 80000
Factory Overhead 80000

Factory 1 overhead = $45 * 1770 = $79650

Factory 2 overhead = $64 * 1250 = $80000

d)

For Factory 1:

Applied Overhead = $79650

Actual Overhead = $81640

Under applied overhead = $1990

For Factory 2:

Applied Overhead = $80000

Actual Overhead = $76800

Over applied overhead = $3200

Note - Post any doubts/queries in comments section

Add a comment
Know the answer?
Add Answer to:
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factorie...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $12,900,000 $10,200,000 Estimated direct labor hours for year 250,000 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $12,900,000 $10,200,000 Estimated direct labor hours for year 250,000 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $674,520 $984,900 Estimated direct labor hours for year 14,700 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $740,250 $735,000 Estimated direct labor hours for year 9,800 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 $381,000 $838,400 13,100 Estimated factory overhead cost for fiscal year beginning March 1 Estimated direct labor hours for year Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $654,780 $1,100,500 Estimated direct labor hours for year 15,500 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $368,600 $999,600 Estimated direct labor hours for year 14,700 Estimated machine hours for...

  • Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $916,180 $907,500 Estimated direct labor hours for year 12,100 24,110 $73,230 $78,480 Estimated...

  • Factory Overhead Rates, Entries, and Account Balance1 Sundance Solar Company operates two factories. The company applies...

    Factory Overhead Rates, Entries, and Account Balance1 Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine heurs are as follows: Factory 1 Factory 2 Estimated factery ovemead cost for fiscal year beginning March 1 $371,450 $850,200 Estimated direct labor hours for year 10,930 Estimated machine hours for...

  • COSTS LoopNet Cityfeet eBook She Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates...

    COSTS LoopNet Cityfeet eBook She Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applles factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of dir labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $613,750 $817,600 Estimated direct labor hours for year...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT