Factory Overhead Rates, Entries, and Account Balance
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows:
Factory 1 | Factory 2 | ||||
Estimated factory overhead cost for fiscal | |||||
year beginning March 1 | $1,018,350 | $889,600 | |||
Estimated direct labor hours for year | 13,900 | ||||
Estimated machine hours for year | 22,630 | ||||
Actual factory overhead costs for March | $81,640 | $76,800 | |||
Actual direct labor hours for March | 1,250 | ||||
Actual machine hours for March | 1,770 |
a. Determine the factory overhead rate for
Factory 1.
$ per machine hour
b. Determine the factory overhead rate for
Factory 2.
$ per direct labor hour
Feedback
a-b. Factory 1 overhead is applied based on machine hours. Factory 2 overhead is applied based on direct labor hours.
c. Journalize the entries to apply factory overhead to production in each factory for March.
Factory 1 | Work in Process | ||
Factory Overhead | |||
Factory 2 | Work in Process | ||
Factory Overhead |
Feedback
c. Increase the work in process and reduce the factory overhead.
d. Determine the balances of the factory overhead accounts for each factory as of March 31, and indicate whether the amounts represent overapplied factory overhead or underapplied factory overhead.
Factory 1 | $ | Debit | Underapplied |
Factory 2 | $ | Credit | Overapplied |
a) Factory overhead rate for Factory 1 = $1,018,350/22630 = $45 per hour
b) Factory overhead rate for Factory 2 = $889,600/13900 = $64 per hour
c) Journal entries for the two factories will be
General Journal | Debit | Credit | |
Factory 1 | Work in Process | 79650 | |
Factory Overhead | 79650 | ||
Factory 2 | Work in Process | 80000 | |
Factory Overhead | 80000 |
Factory 1 overhead = $45 * 1770 = $79650
Factory 2 overhead = $64 * 1250 = $80000
d)
For Factory 1:
Applied Overhead = $79650
Actual Overhead = $81640
Under applied overhead = $1990
For Factory 2:
Applied Overhead = $80000
Actual Overhead = $76800
Over applied overhead = $3200
Note - Post any doubts/queries in comments section
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factorie...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $12,900,000 $10,200,000 Estimated direct labor hours for year 250,000 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $12,900,000 $10,200,000 Estimated direct labor hours for year 250,000 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $674,520 $984,900 Estimated direct labor hours for year 14,700 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $740,250 $735,000 Estimated direct labor hours for year 9,800 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 $381,000 $838,400 13,100 Estimated factory overhead cost for fiscal year beginning March 1 Estimated direct labor hours for year Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $654,780 $1,100,500 Estimated direct labor hours for year 15,500 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $368,600 $999,600 Estimated direct labor hours for year 14,700 Estimated machine hours for...
Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $916,180 $907,500 Estimated direct labor hours for year 12,100 24,110 $73,230 $78,480 Estimated...
Factory Overhead Rates, Entries, and Account Balance1 Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine heurs are as follows: Factory 1 Factory 2 Estimated factery ovemead cost for fiscal year beginning March 1 $371,450 $850,200 Estimated direct labor hours for year 10,930 Estimated machine hours for...
COSTS LoopNet Cityfeet eBook She Factory Overhead Rates, Entries, and Account Balance Sundance Solar Company operates two factories. The company applles factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of dir labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $613,750 $817,600 Estimated direct labor hours for year...