Item - Scissor | Week | ||||||||
0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Gross requirement | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 600 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 50 | 50 | 50 | 50 | 50 | 50 | 50 | 50 | 0 |
Net requirements | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 550 | |
Planned order receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 550 | |
Planned order releases | 0 | 0 | 0 | 0 | 0 | 0 | 550 | 0 | |
Item - Top Assembly | Week | ||||||||
0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Gross requirement | 0 | 0 | 0 | 0 | 0 | 0 | 550 | 0 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 20 | 20 | 20 | 20 | 20 | 20 | 20 | 0 | 0 |
Net requirements | 0 | 0 | 0 | 0 | 0 | 0 | 530 | 0 | |
Planned order receipts | 0 | 0 | 0 | 0 | 0 | 0 | 530 | 0 | |
Planned order releases | 0 | 0 | 0 | 0 | 0 | 530 | 0 | 0 | |
Item - Bottom Assembly | Week | ||||||||
0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Gross requirement | 0 | 0 | 0 | 0 | 0 | 0 | 550 | 0 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 45 | 45 | 45 | 45 | 45 | 45 | 45 | 0 | 0 |
Net requirements | 0 | 0 | 0 | 0 | 0 | 0 | 505 | 0 | |
Planned order receipts | 0 | 0 | 0 | 0 | 0 | 0 | 505 | 0 | |
Planned order releases | 0 | 0 | 0 | 0 | 0 | 505 | 0 | 0 | |
Item - Screw | Week | ||||||||
0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Gross requirement | 0 | 0 | 0 | 0 | 0 | 0 | 550 | 0 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Net requirements | 0 | 0 | 0 | 0 | 0 | 0 | 550 | 0 | |
Planned order receipts | 0 | 0 | 0 | 0 | 0 | 0 | 550 | 0 | |
Planned order releases | 0 | 0 | 0 | 0 | 0 | 550 | 0 | 0 | |
Item - Bend Plastic Grip | Week | ||||||||
0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Gross requirement | 0 | 0 | 0 | 0 | 0 | 530 | 0 | 0 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 90 | 90 | 90 | 90 | 90 | 90 | 0 | 0 | 0 |
Net requirements | 0 | 0 | 0 | 0 | 0 | 440 | 0 | 0 | |
Planned order receipts | 0 | 0 | 0 | 0 | 0 | 440 | 0 | 0 | |
Planned order releases | 440 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Item - Bend Metal Blade | Week | ||||||||
0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Gross requirement | 0 | 0 | 0 | 0 | 0 | 530 | 0 | 0 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 350 | 350 | 350 | 350 | 350 | 350 | 0 | 0 | 0 |
Net requirements | 0 | 0 | 0 | 0 | 0 | 180 | 0 | 0 | |
Planned order receipts | 0 | 0 | 0 | 0 | 0 | 180 | 0 | 0 | |
Planned order releases | 0 | 0 | 0 | 180 | 0 | 0 | 0 | 0 | |
Item - Straight Plastic Grip | Week | ||||||||
0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Gross requirement | 0 | 0 | 0 | 0 | 0 | 0 | 550 | 0 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Net requirements | 0 | 0 | 0 | 0 | 0 | 0 | 550 | 0 | |
Planned order receipts | 0 | 0 | 0 | 0 | 0 | 0 | 550 | 0 | |
Planned order releases | 0 | 550 | 0 | 0 | 0 | 0 | 0 | 0 | |
Item - Straight Metal Bend | Week | ||||||||
0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Gross requirement | 0 | 0 | 0 | 0 | 0 | 505 | 0 | 0 | |
Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on-hand | 150 | 150 | 150 | 150 | 150 | 150 | 0 | 0 | 0 |
Net requirements | 0 | 0 | 0 | 0 | 0 | 355 | 0 | 0 | |
Planned order receipts | 0 | 0 | 0 | 0 | 0 | 355 | 0 | 0 | |
Planned order releases | 0 | 0 | 0 | 355 | 0 | 0 | 0 | 0 |
As all the ordering happens within the planning horizon, it is possible to deliver 600 scissors by day 7.
You're working as a summer intern in the scheduling department at a scissors manufacturer. The production coordinator is out sick and you're in charge of the MRP system until she's back....