The demand for subassembly S is 110 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 1 week to make Z.

Construct a gross material requirements plan.

The product structure. The time-phased product structure. Level 1 2 3 4 5 67 Time in weeks


1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Answer: Demand for Sub-assembly S = 110 units Time -Week 7

The Gross requirements plan for the same is given in the following table:

Materials

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Lead time

V. Required date

Order release

220

220

1 week

W. Required date

Order release

220

220

220

220

3 weeks

X. Required date

Order release

220

220

220

2 weeks

Y. Required date

Order release

110

110

110

2 weeks

Z. Required date

Order release

220

220

1 week

T. Required date

Order release

220

220

1 week

U. Required date

Order release

110

110

110

2 weeks

S. Required date

Order release

110

110

110

2 weeks

Therefore, according to Gross Requirements material plan, 220 units of W and 110 units of Y production are started from day 1 of week 1. 220 units of W are released after 3rd week and 110 units of Y are released after 2nd week

In 2nd week 220 units of X and 220 units of Z production are started. 220 units of X are released after 3rd week and 220 units of 2 are released after 2nd week

At 3rd week – 220 units of Z and 110 units of Y are ready, so production of U which requires 220 units of Z and 110 units of Y is started from 3rd week. 110 units of U are produced bye end of 4th week

Also, in 3rd week – 220 units of production of V is started which are released by end of 3rd week

In 4th week, 220 units of T production is started which requires 220 units of V, 220 units of W and 220 units of X. 220 units of T are produced by end of 4th week

In 5th week – we have 220 units of T and 110 units of U which are required for production of 110 units of S. S requires lead time of 2 weeks and so by end of 6th week 110 units of S are produced

In 7th week – 110 Units of S are made ready

Add a comment
Know the answer?
Add Answer to:
The demand for subassembly S is 110 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of​ V, 1 unit of​ W, and 1 unit of X.​ Finally, each unit of U...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT