ANSWER:
1-2-4=18 days
1-3-4 = 15 days
Step | Critical path (in days) |
activities to crash by day 1 Cost of the crash) |
Cost change | Final total Cost ($) |
1 |
1-2-3-4 (19) 1-2-4 (18) 1-3-4 (15) |
1-2 (30) |
30-90= -60 | 1710-60= 1650 |
2 |
1-2-3-4 (18) 1-2-4 (17) 1-3-4 (15) |
2-3 (40) | 40-90= -50 | 1650-50 = 1600 |
3 |
1-2-3-4 (17) 1-2-4 (17) 1-3-4 (15) |
1-2 (50) 2-3 (45), 2-4 (35) |
50-90 = -40 | 1560 |
4 |
1-2-3-4 (16) 1-2-4 (16) 1-3-4 (15) |
1-2 (70) 2-3 (45) 2-4 (35) |
70-90=-20 | 1540 |
5 |
1-2-3-4 (15) 1-2-4 (15) 1-3-4 (15) |
2-3 (45) 2-4 (35) 1-3 (60) |
45+35+60-90=50 | 1590 |
6 |
1-2-3-4 (14) 1-2-4 (14) 1-3-4 (14) |
2-3 (65) 2-4 (60) 1-3 (60) |
65+60+60-90=95 | 1,685 |
7 | At 13 weeks system is fully crashed | Crash time = 4+6+3 = 13 weeks |
3. The network for shooting a TV commercial as shown in the table has a fixed cost of $90 per day but money can be saved by shortening the project duration. Find the least-cost schedule. Normal Time...