Question

(20 points) A component used in a manufacturing facility is ordered from an outside supplier. Because the component is used i
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer K = 200

                  h = (.005)(.65) = .00325/unit

                  µ h = 3.25/thousand.

                  r = (22, 34, 32, 12, 8, 44, 54, 16, 76, 30)

            a)   Silver Meal Solution (S/M)

                  Start in period 1:

                  C(1) = 200

                  C(2) = [200 + ((3.25)(34)]/2 = 172.8

                  C(3) = [(155.25)(2) + (3.25)(2)(32)]/3 = 183.5     Stop.

                  y1 = r1 + r2 = 56

                  Start in period 3:

                  C(1) = 200

                  C(2) = [200 + (3.25)(12)]/2 = 119.5

                  C(3) = [(2)(119.5) + (2)(3.25)(8)]/3 = 97

                  C(4) = [(3)(97) + (3)(3.25)(44)]/4 = 180     Stop.

                  y3 = r3 + r4 + r5 = 32 + 12 + 8 = 52

                        Start in period 6:

                  C(1) = 200

                  C(2) = [200 + (3.25)(54)]/2 = 187.75

                  C(3) = [(2)(187.75) + (2)(3.25)(16)]/3 = 159.83...

                  C(4) = [(3)(159.833..) + (3)(3.25)(76)]/4 = 305.125   Stop.

                  y6 = r6 + r7 + r8 = 44 + 54 + 16 = 114

                  Obtain y9 = r9 + r10 = 106

                  Silver Meal Solution = (56, 0, 52, 0, 0, 114, 0, 0, 106, 0)

                  Cost = (4)(200) + (3.25)(34 + 20 + 8 + 70 + 16 + 30)

                           = $1378.50

Answer C:-   Least Unit Cost (LUC) method:

                  Start in period 1:

                  C(1) = 200/22 = 9.09

                  C(2) = [200 + (3.25)(34)]/(22 + 34) = 5.54

                  C(3) = [200+(3.25)(34+(2)(32))]/(22+34+32) = 5.89 Stop.

                  y1 = r1 + r2 = 56

                  Start in period 3:

                  C(1) = (200)/(32) = 6.25

                  C(2) = [200 + (3.25)(12)]/(32 + 12) = 5.43

                  C(3) = [200 + (3.25)(12+(2)(8))]/(32+12 8) = 5.60   Stop.

                  y3 = r3 + r4 = 44

                  Start in period 5:

                  C(1) = 200/8 = 25

                  C(2) = [200+(3.25)(44)]/(8 + 44) = 6.60

                  C(3) = [200+(3.25)(44+(54)(2))]/(8+44+54) = 6.55

                  C(4) = [200+(3.25)(44+(54)(2)+(16)(3))]/(8+44+54+16)= 7.97 Stop.

                  y5 = r5 + r6 + r7 = 106

                  Start in period 8:

                  C(1) = 12.5

                  C(2) = 4.9

                  C(3) = 5.3 Stop

                  y8 = r8 + r9 = 92

                  y10 = r10 = 30

Answer d-

Summary of Results

                         Cost

                        S/M $1378.50

                        LUC $1890.50

           

*Note: None of these solutions is optimal. The true optimal solution is (56, 0, 52, 0, 0, 44, 70, 0, 106, 0) at a cost of $1351.00.   Silver Meal obviously comes the closest for this example.

                  LUC solution: (56, 0, 44, 0, 106, 0, 0, 92, 0, 30)

                  Cost = (200)(5)+(3.25)(34 + 12 + 98 + 54 + 76) = $1,890.50.

Add a comment
Know the answer?
Add Answer to:
(20 points) A component used in a manufacturing facility is ordered from an outside supplier. Because the component is used in a variety of end products, the demand is high. Estimated demand (in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • M. P. VanOyen Manufacturing has gone out on bid for a regulator component. Expected demand is...

    M. P. VanOyen Manufacturing has gone out on bid for a regulator component. Expected demand is 700 units per month. The item can be purchased from either Allen Manufacturing or Baker Manufacturing. Their price lists are shown in the table. Ordering cost is $50, and annual holding cost per unit is $4 Allen Quantity Unit Price Quantity $16.00 15.50 Unit Price 1-499 $16.10 15.60 5.10 400-799 1000+ 15.00 a) What is the economic order quantity if price is not a...

  • Hahn Manufacturing purchases a key component of one of its products from a local supplier. The...

    Hahn Manufacturing purchases a key component of one of its products from a local supplier. The current purchase price is $1,500 per unit. Efforts to standardize parts succeeded to the point that this same component can now be used in five different products. Annual component usage should increase from 150 to 850 units. Management wonders whether it is time to make the component in-house, rather than to continue buying it from the supplier. Fixed costs would increase by about $60,000...

  • A juice company purchases components from a variety of sources through their global network of suppliers. They are looki...

    A juice company purchases components from a variety of sources through their global network of suppliers. They are looking to determine their order quantity for PET bottles. They have forecast their demand for PET bottles for the next year to be 1195295 cases. Being a standard component, sales are expected to be constant/uniform over the course of the year. They operate 5 days per week so each year is made up of 260 days. The lead time for PET bottles...

  • SYNOPSIS The product manager for coffee development at Kraft Canada must decide whether to introduce the...

    SYNOPSIS The product manager for coffee development at Kraft Canada must decide whether to introduce the company's new line of single-serve coffee pods or to await results from the product's launch in the United States. Key strategic decisions include choosing the target market to focus on and determining the value proposition to emphasize. Important questions are also raised in regard to how the new product should be branded, the flavors to offer, whether Kraft should use traditional distribution channels or...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT