Calculate the cubic yards of cut and fill for the
following cross section. End areas are provided below. Assume
shrinkage factor = 0.13. Is this a borrow (shortage in earth),
waste(extra earth), or balanced (equal amounts of earth)
project?
Station
Cut(sf)
Fill(sf)
102+00
150.
150
103+00.
150.
150
104+00(B)
175.
175
104+00(A)
10.
10
105+00(B)
11.
11
105+00(A)
45.
45
106+00.
50.
50
106+75.
60.
60
107+00.
70.
70
-> volume of fill is more than volume of cut so it is borrow work.
Calculate the cubic yards of cut and fill for the following cross section. End areas are provided below. Assume shrinkage factor = 0.13. Is this a borrow (shortage in earth), waste(extra earth), or ba...
Part 1 Complete the following Earthwork Sheet Material: Earth and Gravel, Swell Factor: 83 Strip fill(cy Total till och Total cut beyl Adj fill (byl Sum (beyl Mass ordinate 1.23 056 2.37 1.20 2.36 3.07 3.60 3.77 3.09 3.01 4.65 Strip cut (boyil 0.04 1.04 097 3.22 2.08 2.33 2.51 1.85 161 1.74 0.88 109 35.70 5.58 18 3.12 2.03 6.77 2.01 2.53 0.82 1.08 1.20 1.92 1.59 1.82 3.95 3.25 2.74 150 7.42 556 80 End-area End area cut...