Which of the following is NOT true about tools and techniques of Perform Integrated Change Control? They indlude project plan updates O They include esxpert judgment 0 They include change contol...
Which of the following is NOT true about tools and techniques of Perform Integrated Change Control? They indlude project plan updates O They include esxpert judgment 0 They include change contol meetings OA change control board (CCB) is responsible for meeting and reviewing the change requests and approving, rejecting, or other disposition of thoe changes QUESTION 68 All the following are parts of an effective change management plan, EXCEPT Procedures Standards for Report Meeting Lesson Leaned
Which of the following is NOT true about tools and techniques of Perform Integrated Change Control? They indlude project plan updates O They include esxpert judgment 0 They include change contol meetings OA change control board (CCB) is responsible for meeting and reviewing the change requests and approving, rejecting, or other disposition of thoe changes QUESTION 68 All the following are parts of an effective change management plan, EXCEPT Procedures Standards for Report Meeting Lesson Leaned