Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla chip
Fary overeed is located to the three products on the basis of processing hours. The products had the following production bud
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Budgeted volume Processing hours per case
Tortilla chips 6,300 0.10 630
Potato chips 2,700 0.12 324
Pretzels 6,600 0.15 990
Total 15,600 1,944

a.

Single plantwide factory overhead rate = $122,472 / 1,944 = $63 per processing hour.

b.

Total factory overhead Per case factory overhead
Tortilla chips $39,690 (630*$63) $6.3 (39,690/6,300)
Potato chips 20,412 (324*$63) 7.56 (20,412/2,700)
Pretzels 62,370 (990*$63) 9.45 (62,370/6,600)
Total $122,472
Add a comment
Know the answer?
Add Answer to:
Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla...

    Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla chips, potato chips, and pretzels. The company has budgeted the following costs for the upcoming period: Factory depreciation Indirect labor Factory electricity $18,779 46,539 5,307 11,023 26,127 Indirect materials Selling expenses Administrative expenses 14,697 Total costs $122.472 Factory overhead is allocated to the three products on the basis of processing hours. The products had the following production budget and processing hours per case: Budgeted...

  • Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla...

    Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla chips, potato chips, and pretzels. The company has budgeted the following costs for the upcoming period: Factory depreciation $11,668 Indirect labor 28,916 Factory electricity 3,297 Indirect materials 6,849 Selling expenses 16,234 Administrative expenses 9,131 Total costs $76,095 Factory overhead is allocated to the three products on the basis of processing hours. The products had the following production budget and processing hours per case: Budgeted...

  • Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla...

    Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla chips, potato chips, and pretzels. The company has budgeted the following costs for the upcoming period: Factory depreciation Indirect labor $23,995 59,467 6,781 Factory electricity Indirect materials 14,085 Selling expenses 33,385 Administrative expenses 18,779 Total costs $156,492 Factory overhead is allocated to the three products on the basis of processing hours. The products had the following production budget and processing hours per case: Budgeted...

  • Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla...

    Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla chips, potato chips, and pretzels. The company has budgeted the following costs for the upcoming period: Factory depreciation $23,909 Indirect labor 59,251 Factory electricity Indirect materials Selling expenses Administrative expenses 6,757 14,033 33,264 18,711 Total costs $155,925 Factory overhead is allocated to the three products on the basis of processing hours. The products had the following production budget and processing hours per case: Budgeted...

  • Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla...

    Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla chips, potato chips, and pretzels. The company has budgeted the following costs for the upcoming period: Factory depreciation $14,315 Indirect labor 35,476 Factory electricity 4,045 Indirect materials 8,402 Selling expenses 19,916 Administrative expenses 11,203 Total costs $93,357 Factory overhead is allocated to the three products on the basis of processing hours. The products had the following production budget and processing hours per case: Budgeted...

  • Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla...

    Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla chips, potato chips, and pretzels. The company has budgeted the following costs for the upcoming period: Factory depreciation $18,717 Indirect labor 46,385 Factory electricity 5,290 Indirect materials 10,986 Selling expenses 26,041 Administrative expenses 14,648 Total costs $122,067 Factory overhead is allocated to the three products on the basis of processing hours. The products had the following production budget and processing hours per case: Budgeted...

  • eBook Calculator Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack...

    eBook Calculator Single Plantwide Factory Overhead Rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla chips, potato chips, and pretzels. The company has budgeted the following costs for the upcoming period: Factory depreciation $ 31,360 Indirect labor 78,400 Factory electricity 7,840 Indirect materials 35,400 Selling expenses 25,000 Administrative expenses 18,000 $196,000 Total costs Factory overhead is allocated to the three products on the basis of processing hours. The products had the following production budget and processing hours...

  • Single Plantwide Factory Overhead Rate Scrumptious Snacks Inc. manufactures three types of snack foods: tortilla chips,...

    Single Plantwide Factory Overhead Rate Scrumptious Snacks Inc. manufactures three types of snack foods: tortilla chips, potato chips, and pretzels. The company has budgeted the following costs for the upcoming period: Factory depreciation $22,811 Indirect labor 56,533 Factory electricity 6,447 Indirect materials 13,389 Selling expenses 31,738 Administrative expenses 17,852 Total costs $148,770 Factory overhead is allocated to the three products on the basis of processing hours. The products had the following production budget and processing hours per case: Budgeted Volume...

  • Single Plantwide Factory Overhead Rate Scrumptious Snacks Inc. manufactures three types of snack foods: tortilla chips,...

    Single Plantwide Factory Overhead Rate Scrumptious Snacks Inc. manufactures three types of snack foods: tortilla chips, potato chips, and pretzels. The company has budgeted the following costs for the upcoming period: Factory depreciation $10,632 Indirect labor 26,348 Factory electricity 3,005 Indirect materials 6,239 Selling expenses 14,792 Administrative expenses 8,320 Total costs $69,336 Factory overhead is allocated to the three products on the basis of processing hours. The products had the following production budget and processing hours per case: Budgeted Volume...

  • EX 4-3 Single plantwide factory overhead rate Salty Sensations Snacks Company manufactures three types of snack...

    EX 4-3 Single plantwide factory overhead rate Salty Sensations Snacks Company manufactures three types of snack foods: tortilla chips, potato chips, and pretzels. The company has budgeted the following costs for the upcoming period: Factory depreciation $ 31,360 Indirect labor 78,400 Factory electricity 7,840 Indirect materials 35,400 Selling expenses 25,000 Administrative expenses 18,000 Total costs $196,000 Factory overhead is allocated to the three products on the basis of processing hours. The products had the following production budget and processing hours...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT