Question

Under what circumstances is the ERR a more appropriate method than an IRR to evaluate a project? O A. When the IRR is much gr

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWERS TO THE FOLLOWING QUESTIONS ARE GIVEN IN BOLD AND CAPITAL LETTERS under what circumstances is the ERR more appropriate method than IRR to evaluate a project ANSWER is C WHEN THE LENGTH OF THE PROJECT IS GREATER THAN 20 YEARS    If the future worth is greater than zero what does it mean about the project? Answer is A THE PROJECT SHOULD BE CONSIDERED FOR FUNDING If the projects present worth is less than zero.what dose that mean about the project annual worth and future worth? Answer is C THE ANNUAL WORTH AND FUTURE WORTH ARE BOTH LESS THAN ZERO. The internal rate of return (IRR) is a rate of return at which what is true? Answer is A PRESENT WORTH =0 The simple payback period is a measure of what? Answer is A LIQUIDITY.

Add a comment
Know the answer?
Add Answer to:
Under what circumstances is the ERR a more appropriate method than an IRR to evaluate a project? O A. When the IRR i...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Under what circumstances is the ERR a more appropriate method than an IRR to evaluate a​...

    Under what circumstances is the ERR a more appropriate method than an IRR to evaluate a​ project? A. When the IRR is much greater than the MARR B. When the length of the project is greater than 20 years C. When the IRR is much less than the MARR If the future worth is greater than​ zero, what does that mean about the​ project? A. The project will not be profitable B. The project should be considered for funding C....

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Celestial Crane Cosmetics is analyzing a project that requires an initial investment of $3,000,000. The project's expected cash flows are: Year Year 1...

  • Dropdown option: (accept, reject) The IRR evaluation method assumes that cash flows from the project are...

    Dropdown option: (accept, reject) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Cute Camel Woodcraft Company is analyzing a project that requires an initial investment of $3,225,000. The project's expected cash...

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes more reasonable assumption other than the project's IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $3,000,000. The project's expected cash flows are: Year Cash Flow...

  • Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR...

    Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR Cash Flow......($200).....$850....($700)......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Accept the project because the payback is short b. Accept the project because the NPV is greater than zero c. Reject the project because the IRR is less than the required rate of return d. Reject the project because...

  • economic. asap Page 4 of 6 Problem 4 A capital investment of $25,000 is made in a project that will produce uniform...

    economic. asap Page 4 of 6 Problem 4 A capital investment of $25,000 is made in a project that will produce uniform annual revenues of $5,000 for 10 years, and then the project terminates. If the minimum attractive rate (MARR) is 10%. 1) Draw a cash flow diagram 2) What is the present worth of this project? 3) Find the internal rate of return (IRR) if a) Salvage value is zero. b) Salvage value is $8.000. 4) If the external...

  • (NPV, PI, and IRR calculations) Fijisawa Inc. is considering a major expansion of its product line...

    (NPV, PI, and IRR calculations) Fijisawa Inc. is considering a major expansion of its product line and has estimated the following free cash flows associated with such an expansion. The initial outlay would be $1,800,000, and the project would generate incremental free cash flows of $600,000 per year for 5 years. The appropriate required rate of return is 8 percent. a. Calculate the NPV. b. Calculate the Pl. c. Calculate the IRR. d. Should this project be accepted? a. What...

  • Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year...................0..............1...............2...........IRR...

    Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year...................0..............1...............2...........IRR Cash Flow.....($200).....$850.......($700).......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Reject the project because the NPV is less than zero b. Accept the project because the IRR is greater than zero c. Accept the project because the NPV is greater than zero d. Accept the project because the payback...

  • 4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...

    4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $2,750,000. The...

  • 4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...

    4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $3,000,000....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT