Question

Question 7 The Family Entertainment Group is about to begin the production of its most Ebo Whyte, ensive) movie of the year.

Please the question consists of (a) , (b) and (c). I need the crashing part which is the (c) than everything. Is very urgent

0 0
Add a comment Improve this question Transcribed image text
Answer #1

As asked, solving for part c

Activity IP Normal time Crash time Normal cost Crash cost Crash slope Max crash Crashed Final time Start Finish
A - 5 3 24 36 6 2 1 4 0 4
B - 3 2 13 25 12 1 0 3 0 3
C A 4 2 21 29 4 2 0 4 4 8
D A 6 3 30 50 6.666666667 3 0 6 4 10
E B 5 4 26 36 10 1 0 5 3 8
F B 7 4 35 57 7.333333333 3 0 7 3 10
G C,E 9 5 30 53 5.75 4 1 8 8 16
H D,F 8 6 35 51 8 2 2 6 10 16
Total time 16
Normal cost 214
Crash cost 27.75
Total cost 241.75

We begin by determining the critical path. That is A-D-H with a duration of 19 weeks. Next we need to crash one of the activities on this critical path that will be the cheapest option. This is why we determined the crash slope. It is the cost to crash each activity for a week. For example to reduce activity A from 5 weeks to 3 weeks it will cost us additional 36-24 = 12 mil. This means that the crash slope is 6 mil per week.

Now determine the cheapest option along critical path. That is activity A. Once we crash activity A by 1 week, we will also notice that ACG reduces to 17 days. However our critical path remains unchanged.

Next, we crash another activity on critical path. Since the dependency of the path is now bottlenecked by F, we cannot crash activity A anymore to reduce time. Now we need to crash activity H. This will create two critical paths. ADH and BEG. The total duration is 17 weeks

Now we need to crash two activities in order to reach 16 week time. Here we will crash H by another week and G by one week. This will create two critical paths with a total duration of 16 weeks.

The normal cost would have been 214 million. However, the additional cost is the crash cost of 27.75 million.

Add a comment
Know the answer?
Add Answer to:
Please the question consists of (a) , (b) and (c). I need the crashing part which is the (c) than everything. Is ver...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT