Please the question consists of (a) , (b) and (c). I need the crashing part which is the (c) than everything. Is very urgent
As asked, solving for part c
Activity | IP | Normal time | Crash time | Normal cost | Crash cost | Crash slope | Max crash | Crashed | Final time | Start | Finish |
A | - | 5 | 3 | 24 | 36 | 6 | 2 | 1 | 4 | 0 | 4 |
B | - | 3 | 2 | 13 | 25 | 12 | 1 | 0 | 3 | 0 | 3 |
C | A | 4 | 2 | 21 | 29 | 4 | 2 | 0 | 4 | 4 | 8 |
D | A | 6 | 3 | 30 | 50 | 6.666666667 | 3 | 0 | 6 | 4 | 10 |
E | B | 5 | 4 | 26 | 36 | 10 | 1 | 0 | 5 | 3 | 8 |
F | B | 7 | 4 | 35 | 57 | 7.333333333 | 3 | 0 | 7 | 3 | 10 |
G | C,E | 9 | 5 | 30 | 53 | 5.75 | 4 | 1 | 8 | 8 | 16 |
H | D,F | 8 | 6 | 35 | 51 | 8 | 2 | 2 | 6 | 10 | 16 |
Total time | 16 | ||||||||||
Normal cost | 214 | ||||||||||
Crash cost | 27.75 | ||||||||||
Total cost | 241.75 |
We begin by determining the critical path. That is A-D-H with a duration of 19 weeks. Next we need to crash one of the activities on this critical path that will be the cheapest option. This is why we determined the crash slope. It is the cost to crash each activity for a week. For example to reduce activity A from 5 weeks to 3 weeks it will cost us additional 36-24 = 12 mil. This means that the crash slope is 6 mil per week.
Now determine the cheapest option along critical path. That is activity A. Once we crash activity A by 1 week, we will also notice that ACG reduces to 17 days. However our critical path remains unchanged.
Next, we crash another activity on critical path. Since the dependency of the path is now bottlenecked by F, we cannot crash activity A anymore to reduce time. Now we need to crash activity H. This will create two critical paths. ADH and BEG. The total duration is 17 weeks
Now we need to crash two activities in order to reach 16 week time. Here we will crash H by another week and G by one week. This will create two critical paths with a total duration of 16 weeks.
The normal cost would have been 214 million. However, the additional cost is the crash cost of 27.75 million.
Please the question consists of (a) , (b) and (c). I need the crashing part which is the (c) than everything. Is ver...