For this , first we need to calculate NPV/pill for each project
For Commodus, NPV/pill = $46900/14 = $3350
For Caligula, NPV/pill = $71000/20 = $3550
For Nero, NPV/pill = $27750/5 = $5550
For Elagabalus, NPV/pill = $70300/19 = $3700
The NPV/pill is highest for Project Nero, so 5 pills must first be alloted to Nero. As the projects are non-repeatable, next 19 pills should be alloted to project Elagabalus, which has the second highest NPV/pill. Now, we have only 11 (35-5-19 = 11) pills left, which we can allott to Project Caligla with the third highest NPV/pill.
So, total achievable NPV
= NPV of Nero + NPV of Elagabalus + partial (11/20 ) NPV of Caligula
=$27750+$70300 + $11/20*71000
=$98050+$39050 =
$137,100