Answer 1 .Calculation of CBM
CBM = Length (cm) x Width (cm) x Height (cm) / 1,000,000 = (100 x 100 x 100) / 1,000,000 = 1 CBM
Answer 2 .Pieces in 1 40 foot container
As per above calculation 1 container (which contains 10 pcs per container) can be placed in 1 CBM.
Quantity in 1 shipment is 50 CBM.
Hence total pieces = 10 pieces x 50 CBM = 500 pieces
Answer 3 .Freight for each piece
Total Freight = $.5,000
Freight per piece = $.5000 / 500 pieces = $.10 per piece
Answer 4 .CFR Price
Particulars | $ | Formula | Index |
Unit Product cost in NTD | 300 | Given | i |
Exchange rate | 30 | Given | ii |
Unit Product cost in USD | 10 | i / ii | iii |
Freight | 10 | Answer 3 | iv |
Total Cost | 20 | iii + iv | v |
Profit | 20 | vi-v | vii |
Selling Price | 40 | v/50% | vi |
Part IV: Use the following data for price calculation. 4 points for each answer. Write your answers in the blanks (16%)...
Part III Question 29-36, Short Answers. 12%. Two(2) points for each answer. Write your answer in the blanks. 1. The following two sentences are price quotes, but EACH of them has ONE error. Please underline or mark the error and write the reason in the blank (1). Dollar 50 per box CFR New York, partial shipment prohibited 29 (2). EURO 25, FOB Keelung, shipment within 20 days after receiving L/C. 30