2.
Simple payback = 2000 / 1000 = 2 yrs
option A is correct answer
3.
Present worth of cash flows for 2 yrs = 1000 * (P/A, 10%,2) = 1000 * 1.735537 = 1735.54
Present worth of cash flows for 3 yrs = 1000 * (P/A, 10%,3) = 1000 * 2.486852 = 2486.85
Using interpolation
n = 3 - (2486.85-2000) / (2486.85 - 1735.54)
n = 3 - 486.85 / 751.31
n = 3 - 0.648 = 2.35 yrs
this is nearest to option d. 2.33 yrs, therefore correct answer is option d
A proposed project has the following costs and benefits: 2. Benefits Year Costs $2,000 0 to b d $1,000 1,000 1,000...
t. b years. Using the information in question #6, and linear interpolation, the project's discounted payback period is most nearly a. 3.62 years. b. 2.26 years. c. 2.05 years. d. 3.41 years. e. 2.89 years. onuGe at the nefits: A proposed project has the following costs and bene Year Costs Benefits 0 $2,000 $1,000 500 1,000 2,000 2,000 Assuming an interest A 2 years. B3 years C. 4 years D. 5 years E. 6 years rate of 10 %, the...
24. If a project has: year 0 -500 year 1- $200 year 2 for this project is: a) 2 years b) 2.5 years c)3 years d) 3.5 years $200 and year 3- $200, then the payback period 25. A project has an initial cost of -10,000. Cash flows of 3,000 will be generated for the next 7 years. If required return is 10%; what is the NPV of this project a) $4,605 b) $8,605 c) $10,605 d) $14,605 24. If...
24. Which of the following costs are variable? 10,000 Units 30,000 Units $100,000 40,000 90,000 50,000 Cost $300,000 240,000 90,000 150,000 2. 4. A) only 2 B) only 1 C) 1 and 2 D) 1 and4 25. Eddy Company is starting business and is unsure of whether to sell its product assembled or unassembled. The unit cost of the unassembled product is $60 and Eddy Company would sell it for $135. The cost to assemble the product is estimated at...