Question

CE413 CONSTRUCTION METHODS Due 4/24/2017 I. A contractor has a five-month project with the expected direct costs as follows: 1 month 25,000, 2d month $40,000, 3d month $65,000, 4th month $80,000, and 5th month $30,000. It is assumed that ( 1 ) the monthly indirect cost is $6,000, (b) retainage is 10% for the first three months, and 0% thereafter; (c) the markup is 25%; and, (d) the monthly interest rate is 1%. The contractor submits payment requests at the end of each month, and payments are received at the end of the next month. The accumulated retainage will be paid to the contractor with the last payment. 1) 2) 3) Create an overdraft calculation table. Draw an overdraft profile plot. Calculate the present values of profits at interest rates 0%, 6%, and 10%.
0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
CE413 CONSTRUCTION METHODS Due 4/24/2017 I. A contractor has a five-month project with the expected direct costs as...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 12.3 Given the following data with the direct costs for each activity as shown, calculate the...

    12.3 Given the following data with the direct costs for each activity as shown, calculate the ROR of the contractor. Assume that (a) the markup is 15%; (b) retainage is 5% on the first 50% of worth, and 0% thereafter; (c) payment requests are submitted at the end of each month, and payments are received one month later; and (d) the finance charge is 1% per month of the amount of the overdraft at the end of the month Timing...

  • CE 210 please show all work TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct...

    CE 210 please show all work TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000 $65,000 $75,000 $15,000 ndirect cost 5,000 5.000 5.000 5.000 Subtotal 30,000 70,000 80,000 20,000 Markup (25%) 7.500 17.500 20,000 5.000 Total billed 37,500 87,500 100,000 25,000 Retainage withheld (10%) 3.750 8,750 Payment received $20,000 $33,750 $78,750 $100,000 Total cost to date 30,000 100,000 180,000 200,000 200,000 Total amount billed to date 37,500 125,000 225,000 250,000 250,000 Total paid to date $20,000 $53,750...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT