Overhead rate = 96000/40000+3 = 5.40 per labor hour
Overhead applied = Actual overhead*Overhead rate = 100*5.4 = $540
So answer is a) $540
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on dir...
Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $96.000 Variable manufacturing overhead per direct labor- $ 3.00 hour Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct laber-hours Direct materiale Direct labor cost 100 $ 755...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data Total direct labor-hours Total fixed manufacturing overhead cost Variable nanufacturing overhead per direct labor-hour 40,000 96,000 $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 두 755 $4,000 The...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor- hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $96,000 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 $ 755 $4,000...
12 Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor hour 40,000 $96,000 $ 3.00 02:0753 Recently, Job P951 was completed with the following characteristics Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 72,000 Total fixed manufacturing overhead cost $ 223,200 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 20 Total direct labor-hours 100 Direct materials $ 890 Direct labor cost $...
Help Save & Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $96,00 Variable manufacturing overhead per direct labor-hour $ 3.ee Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 1ee $...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 101,000 Total fixed manufacturing overhead cost $595,900 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 25 100 $ 840 $10,100...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 72,000 Total fixed manufacturing overhead cost $ 223,200 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 20 Total direct labor-hours 100 Direct materials $ 890 Direct labor cost $...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 72,000 $223,200 $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 $ 890 $7,200 The...
12 Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: 8 01:12:23 Total direct labor-hours 101,000 Total fixed manufacturing overhead cost $595,900 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: 25 Number of units in the job Total direct labor-hours Direct materials Direct labor cost 100 $...