Overhead rate 200% =1220000/610000
A
Job 2-1 364000 =182000*200%
Job 2-2 614000 =307000*200%
Job 2-3 264000 =132000*200%
B
Actual manufacturing overhead 1250000
Manufacturing overhead applied 1242000 =364000+614000+264000
Underapplied manufacturing overhead 8000
Add a comment
Know the answer?
Add Answer to:
Aspen Company estimates its manufacturing overhead to be $1,220,000 and its direct labor costs to be $610,000 for year...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Aspen Company estimates its manufacturing overhead to be $848,000 and its direct labor costs to be...

    Aspen Company estimates its manufacturing overhead to be $848,000 and its direct labor costs to be $530,000 for year 2. Aspen worked on three jobs for the year. Job 2-1, which was sold during year 2, had actual direct labor costs of $166,000. Job 2-2, which was completed, but not sold at the end of the year, had actual direct labor costs of $291,000. Job 2-3, which is still in work-in-process inventory, had actual direct labor costs of $116,000. Actual...

  • Aspen Company estimates its manufacturing overhead to be $765,000 and its direct labor costs to be...

    Aspen Company estimates its manufacturing overhead to be $765,000 and its direct labor costs to be $510,000 for year 2. Aspen worked on three jobs for the year. Job 2-1, which was sold during year 2, had actual direct labor costs of $162,000. Job 2-2, which was completed, but not sold at the end of the year, had actual direct labor costs of $287,000. Job 2-3, which is still in work-in-process inventory, had actual direct labor costs of $112,000. Actual...

  • Aspen Company estimates its manufacturing overhead to be $1,170,000 and its direct labor costs to be...

    Aspen Company estimates its manufacturing overhead to be $1,170,000 and its direct labor costs to be $600,000 for year 2. Aspen worked on three jobs for the year. Job 2-1, which was sold during year 2, had actual direct labor costs of $180,000. Job 2-2, which was completed, but not sold at the end of the year, had actual direct labor costs of $305,000. Job 2-3, which is still in work-in-process inventory, had actual direct labor costs of $130,000. Actual...

  • Aspen Company estimates its manufacturing overhead to be $635,000 and its direct labor costs to be...

    Aspen Company estimates its manufacturing overhead to be $635,000 and its direct labor costs to be $508,000 for year 2. Aspen worked on three jobs for the year. Job 2-1, which was sold during year 2, had actual direct labor costs of $326,600. Job 2-2, which was completed, but not sold at the end of the year, had actual direct labor costs of $195,960. Job 2-3, which is still in work-in-process inventory, had actual direct labor costs of $130,640. Actual...

  • Aspen Company estimates its manufacturing overhead to be $506,000 and its direct labor costs to be...

    Aspen Company estimates its manufacturing overhead to be $506,000 and its direct labor costs to be $506,000 for year 2. Aspen worked on three jobs for the year. Job 2-1, which was sold during year 2, had actual direct labor costs of $244,650. Job 2-2, which was completed, but not sold at the end of the year, had actual direct labor costs of $407,750. Job 2-3, which is still in work-in-process inventory, had actual direct labor costs of $163,100. Actual...

  • Aspen Company estimates its manufacturing overhead to be $553,300 and its direct labor costs to be...

    Aspen Company estimates its manufacturing overhead to be $ 553,300 and its direct labor costs to be $ 503,000 for year 2. Aspen worked on three jobs for the year. Job 2-1, which was sold during year 2, had actual direct labor costs of $ 370,000. Job 2-2, which was completed, but not sold at the end of the year, had actual direct labor costs of $ 222,000. Job 2-3, which is still in work-in-process inventory, had actual direct labor...

  • Aspen Company estimates its manufacturing overhead to be $646,250 and its direct labor costs to be...

    Aspen Company estimates its manufacturing overhead to be $646,250 and its direct labor costs to be $517,000 for year 2. Aspen worked on three jobs for the year. Job 2-1, which was sold during year 2, had actual direct labor costs of $151064. Job 2-2, which was completed, but not sold at the end of the year, had actual direct labor costs of $380,944. Job 2-3, which is still in work-in-process inventory, had actual direct labor costs of $124,792. Actual...

  • Aspen Company estimated its manufacturing overhead to be $1,073,000 and its direct labor costs to be...

    Aspen Company estimated its manufacturing overhead to be $1,073,000 and its direct labor costs to be $580,000 for year 2. Aspen worked on three jobs for the year. Job 2-1, which was sold during year 2, had actual direct labor costs of $176,000. Job 2-2, which was completed, but not sold at the end of the year, had actual direct labor costs of $301,000. Job 2-3, which is still in work-in-process inventory, had actual direct labor costs of $126,000. Actual...

  • Aspen Company estimates its manufacturing overhead to be $625,000 and its direct labor costs to be...

    Aspen Company estimates its manufacturing overhead to be $625,000 and its direct labor costs to be $500,000 for year 2. Aspen worked on three jobs for the year. Job 2-1, which was sold during year 2, had actual direct labor costs of $195,000. Job 2-2, which was completed, but not sold at the end of the year, had actual direct labor costs of $325,000. Job 2-3, which is still in work-in-process inventory, had actual direct labor costs of $130,000. Actual...

  • Aspen Company estimates its manufacturing overhead to be $608,400 and its direct labor costs to be $507,000 for year 2....

    Aspen Company estimates its manufacturing overhead to be $608,400 and its direct labor costs to be $507,000 for year 2. Aspen worked on three jobs for the year. Job 2-1, which was sold during year 2, had actual direct labor costs of $272,000. Job 2-2, which was completed, but not sold at the end of the year, had actual direct labor costs of $340,000. Job 2-3, which is still in work-in-process inventory, had actual direct labor costs of $68,000. Actual...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT