High Low method-Calculation of variable cost per maintenance hour | ||||
Change in cost | Cost at high point minus cost at low point | 3600 | Variable cost per maintenance hour | 200.00 |
Change in volume | Volume at high point minus volume at low point | 18 | ||
Total cost at the high point | 6950 | |||
Variable costs at the high point: | ||||
Volume at the high point | 24 | |||
Variable cost per maintenance hour | 200.00 | |||
Total Variable costs at the high point | 4800 | |||
Total fixed costs | 2150 | |||
Total cost at the low point | 3350 | |||
Variable costs at the low point: | ||||
Volume at the low point | 6 | |||
Variable cost per maintenance hour | 200.00 | |||
Total Variable costs at the low point | 1200 | |||
Total fixed costs | 2150 |
The following informations sable for company's maintenance cost over the last seven months Using the high-low method es...
The following information is available for a company's maintenance cost over the last seven months. Maintenance Cost $ 5,550 8,430 Month June July August September October November December Units Produced 100 190 110 140 200 230 50 5,870 6,830 8,750 9,710 3,950 Using the high-low method, estimate both the fixed and variable components of its maintenance cost. High-Low method - Calculation of variable cost per maintenance hour Total cost at the high point Variable costs at the high point: Volume...
The following information is available for a company's maintenance cost over the last seven months. Month June July August September October November December Units Produced 90 180 120 150 210 240 Maintenance Cost $5,450 6,900 5, 100 6,000 6,900 8, 100 3,600 60 Using the high-low method, estimate both the fixed and variable components of its maintenance cost. Change in cost Change in volume High-Low method - Calculation of variable cost per maintenance hour Cost at high point minus cost...
please help The following information is available for a company's maintenance cost over the last seven months. Month June July August September October November December Units Produced 90 180 120 150 210 240 60 Maintenance Cost $ 4,830 7,620 5,760 6,690 8,550 9,480 3,900 Using the high-low method, estimate both the fixed and variable components of its maintenance cost. High-Low method - Calculation of variable cost per maintenance hour Total cost at the high point Variable costs at the high...
Check my work The following information is available for a company's maintenance cost over the last seven months. Month July August September October November December Maintenance Hours Maintenance Cont 4,240 5.500 4,660 5,290 6.550 7,180 Using the high-low method, estimate both the fixed and variable components of its maintenance cost High-Low method - Calculation of variable cost per maintenance hour Total cost at the high point high point Variable costs at the high point Volume at the high point Variable...
QS 18-3 Cost behavior estimation-high-low method LO P1 The following information is available for a company's maintenance cost over the last seven months. Month June July August September October November December Maintenance Hours Maintenance Cost 3,710 5,240 4,220 4,730 5,750 6,260 3,200 15 Using the high-low method, estimate both the fixed and variable components of its maintenance cost. Using the high-low method, estimate both the fixed and variable components of its maintenance cost. High-Low method - Calculation of variable cost...
QS 18-3 Cost behavior estimation-high-low method LO P1 The following information is available for a company's maintenance cost over the last seven months Units Produced 100 Month June July August September October November December 190 110 140 200 230 Maintenance cost $ 5,250 7.850 5.540 6,41e 8.15 9.02e 3,800 Using the high-low method, estimate both the fixed and variable components of its maintenance cost High Low method - Calculation of variable cost per maintenance hour Total cost at the high...
The following information is available for a company’s maintenance cost over the last seven months. Month Maintenance Hours Maintenance Cost June 9 $ 3,950 July 18 5,750 August 12 4,550 September 15 5,150 October 21 6,350 November 24 6,950 December 6 3,350 Using the high-low method, estimate both the fixed and variable components of its maintenance cost. High- Low method- Calculation of variable cost per maintenance hour
please help me get this right :/ The following information is available for a company's maintenance cost over the last seven months. Maintenance Maintenance Month Hours Cost June $ 5,450 July 18 6,900 August 12 5,100 September 6,000 October 6,900 November 8,100 December 3,600 15 Using the high-low method, estimate both the fixed and variable components of its maintenance cost. High-Low method - Calculation of variable cost per maintenance hour Total cost at the high point Variable costs at the...
Check my QS 21-3 Cost behavior estimation-high-low method LO P1 The following information is available for a company's maintenance cost over the last seven months intenance Maintenance Cos une July August September October 18 12 15 21 24 s5,e7e 8,130 6,090 7,110 9,158 10,170 4,850 December Using the high-low method, estimate both the fixed and variable components of its maintenance cost Total cost at the high point Variable costs at the high point Volume at the high poin Varlable cost...
The following information is available for a company’s maintenance cost over the last seven months. Month Units Produced Maintenance Cost June 110 $ 5,320 July 170 7,300 August 130 5,980 September 160 6,970 October 220 8,950 November 250 9,940 December 70 4,000 Using the high-low method, estimate both the fixed and variable components of its maintenance cost.