Question

Marvel Parts, Inc., manufactures auto accessories. One of the companys products is a set of seat covers that can be adjusted$ $ $ 47,500 F 42,500U 5,000 1. Materials price variance Materials quantity variance 2. Labor rate variance Labor efficiency

Please solve second part of 2 and all of 3. I got 4,000 for Labor efficiency variance, but that is not correct and I don't know why.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Data for Resource Variance

Resource

Standard (2,500 units)

Actual (2,500 units)

Quantity

Rate

Total Cost

Quantity

Rate

Total Cost

Direct Material

7,500 yards

$ 8.50

$ 63,750

12,500 yards

$ 4.70

$ 58,750

Direct Labour

1,250 hours

$ 10.00

$ 12,500

800 hours

$ 16.25

$ 13,000

Variable Overheads

1,250 hours

$ 5.00

$ 6,250

800 hours

$ 8.75

$ 7,000

Answer 1)

Material Price Variance

Material price variance = (Standard Price per unit – Actual Price per unit) X Actual Quantity consumed

                                                             = ($ 8.50 - $ 4.70) X 12,500 yards

                                                             = $ 47,500 (Favourable)

Therefore Material price variance is $ 47,500 (favourable)

Material Quantity Variance (Material Usage Variance)

Material quantity variance = (Standard Quantity – Actual Quantity) X Standard Price per unit

                                                             = (7,500 yards – 12,500 yards) X $ 8.50 per yard

                                                             = $ 42,500 (Unfavourable)

Therefore Material Quantity variance is $ 42,500 (Unfavourable)

Answer 2)

Labour Rate Variance

Labour rate variance = (Standard rate per hour – Actual rate per hour) X Actual Direct labour hours

                                           = ($ 10.00 - $ 16.25) X 800 labour hours

                                           = $ 5,000 (Unfavourable)

Therefore Labour Rate variance is $ 5,000 (Unfavourable)

Labour Efficiency variance

Labour Efficiency variance = (Standard labour hours for actual output – Actual labour hours for actual output) X Standard rate per labour hour

                                                             = (1,250 labour hours – 800 labour hours) X $ 10.00 per hour

                                                             = $ 4,500 (favourable)

Therefore Labour efficiency variance is $ 4,500 (favourable)

Answer 3)

Variable overhead Rate Variance

Variable overhead rate variance = (Standard rate per hour – Actual rate per hour) X Actual Direct labour hours

                                           = ($ 5.00 - $ 8.75) X 800 labour hours

                                           = $ 3,000 (Unfavourable)

Therefore Variable overhead Rate variance is $ 3,000 (Unfavourable)

Variable overhead Efficiency variance

Variable overhead Efficiency variance = (Standard hours for actual output – Actual hours for actual output) X Standard Variable overhead rate per hour

                                                             = (1,250 labour hours – 800 labour hours) X $ 5.00 per hour

                                                             = $ 2,250 (favourable)

Therefore Variable overhead efficiency variance is $ 2,250 (favourable)

Working Notes:

Material:

Actual price per yard of material

Actual price per yard of material = Actual material cost/Actual yards of material consumed

                                                          = $ 58,750/ 12,500 yards

                                                         = $ 4.70 per yard

Standard price per yard of material

Standard price per yard of material = Standard material cost/Standard yards of material consumed

                                                          = $ 54,825/ (2,150 sets X 3.00 yards per set)

                                                          = $ 54,825/ 6,450 yards

                                                         = $ 8.50 per yard

Standard Quantity for actual output

Standard Quantity for actual output = Standard Material required per unit X Actual number of units produced

                                                                  = 3.00 yards per set of covers X 2,500 sets

                                                                 = 7,500 yards                 

Standard Material cost for actual output

Standard Material cost for actual output = Standard Quantity for actual output X Standard cost per yard

                                                                        = 7,500 yards X $ 8.50 per yard

                                                                        = $ 63,750  

Labour:

Actual rate per direct labour hour

Actual rate per direct labour = Actual labour cost/Actual direct labour hours worked

                                                          = $ 13,000/ 800 direct labour hours

                                                         = $ 16.25 per direct labour hour

Standard rate per direct labour hour

Standard rate per direct labour hour = Standard labour cost/Standard direct labour hours worked

                                                          = $ 10,750/ (1,075 direct labour hours)

                                                          = $ 10.00 per direct labour hour

Standard direct labour hours per unit

Standard direct labour hours per unit = Total Standard direct labour hours/Standard units produced

                                                          = 1,075 direct labour hours/ 2,150 set of covers

                                                         = 0.50 direct labour hour per set of covers

Standard Direct labour hours for actual output

Standard direct labour hours for actual output = Standard direct labour hour required per unit X Actual number of units produced

                                                                  = 0.50 hour per set of covers X 2,500 sets

                                                                 = 1,250 direct labour hours

Standard labour cost for actual output

Standard labour cost for actual output = Standard direct labour hours for actual output X Standard rate per direct labour hour

                                                                        = 1,250 direct labour hours X $ 10.00 per direct labour hour

                                                                        = $ 12,500  

Variable Overheads:

Actual variable overhead rate per hour

Actual variable overhead rate per labour = Actual variable overhead cost/Actual direct labour hours worked

                                                          = $ 7,000/ 800 direct labour hours

                                                         = $ 8.75 per direct labour hour

Standard variable overhead rate per hour

Standard variable overhead rate per hour = Standard variable overhead cost/Standard direct labour hours worked

                                                          = $ 5,375/ (1,075 direct labour hours)

                                                          = $ 5.00 per direct labour hour

Standard variable overhead cost for actual output

Standard variable overhead cost for actual output = Standard direct labour hours for actual output X Standard variable overhead rate per direct labour hour

                                                                        = 1,250 direct labour hours X $ 5.00 per direct labour hour

                                                                        = $ 6,250  

Add a comment
Know the answer?
Add Answer to:
Please solve second part of 2 and all of 3. I got 4,000 for Labor efficiency variance, but that is not correct and I do...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT