Question

Yosko Company expects to produce 1,990 units in January and 1,957 units in February. Yosko budgets six direct labor hours per

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Direct Labor hours Budget
Particulars January February
Expected production 1990 1957
DLH per unit 6 6
DLH needed for prod. 11940 11742
Direct Labor cost budget
Particulars January February
DLH needed for prod. 11940 11742
DL cost per hour $           15.00 $           15.00
Direct labor cost $ 179,100.00 $ 176,130.00
Add a comment
Know the answer?
Add Answer to:
Yosko Company expects to produce 1,990 units in January and 1,957 units in February. Yosko budgets six direct labor hou...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Yordi Company expects to produce 1,660 units in January and 1,941 units in February. Yordi budgets...

    Yordi Company expects to produce 1,660 units in January and 1,941 units in February. Yordi budgets six direct labor hours per unit. Direct labor costs average $19 per hour. Prepare Yordi's direct labor budget for January and February Begin by preparing the direct labor budget for January and February through the total direct labor hours needed for production line and then complete the budget by calculating the budgeted direct labor cost Yordi Company Direct Labor Budget Two Months Ended January...

  • Yem expects to produce 1,700 units in January and 2,180 units in February. The company budgets...

    Yem expects to produce 1,700 units in January and 2,180 units in February. The company budgets 3 pounds per unit of direct materials at a cost of $25 per pound. Indirect materials are insignificant and not considered for budgeting purposes. The balance in the Raw Materials Inventory account (all direct materials) on January 1 is 5,700 pounds. Yem desires the ending balance in Raw Materials Inventory to be 20% of the next month's direct materials needed for production. Desired ending...

  • Yordi Company expects to produce 2,040 units in January that will require 10,200 hours of direct...

    Yordi Company expects to produce 2,040 units in January that will require 10,200 hours of direct labor and 2,300 units in February that will require 11,500 hours of direct labor. Yordi budgets $4 per unit for variable manufacturing overhead; $1,600 per month for depreciation; and $130,770 per month for other fixed manufacturing overhead costs. Prepare Yordi's manufacturing overhead budget for January and February, including the predetermined overhead allocation rate using direct labor hours as the allocation base. (Abbreviations used: VOH...

  • Yem Company expects to produce 2,030 units in January that will require 4,060 hours of direct...

    Yem Company expects to produce 2,030 units in January that will require 4,060 hours of direct labor and 2,280 units in February that will require 4,560 hours of direct labor. Yem budgets $12 per unit for variable manufacturing overhead; $1,100 per month for depreciation; and $3,210 per month for other fixed manufacturing overhead costs. Prepare Yem's manufacturing overhead budget for January and February, including the predetermined overhead allocation rate using direct labor hours as the allocation base. (Abbreviations used: VOH...

  • Bennett Company expects to produce 2.030 units in January that will require 8,120 hours of direct...

    Bennett Company expects to produce 2.030 units in January that will require 8,120 hours of direct labor and 2,210 units in February that will require 8,840 hours of direct labor. Bennett budgets $10 per unit for variable manufacturing overhead: $2,100 per month for depreciation; and $78,460 per month for other fixed manufacturing overhead costs. Prepare Bennett's manufacturing overhead budget for January and February, including the predetermined overhead allocation rate using direct labor hours as the allocation base. (Abbreviations used: VOH...

  • expects to produce 1,700 units in January and 2,084 units in February. The company budgets $...

    expects to produce 1,700 units in January and 2,084 units in February. The company budgets $ 35 per unit for direct materials. Indirect materials are insignificant and not considered for budgeting purposes. The balance in the Raw Materials Inventory account​ (all direct​ materials) on January 1 is $47,500. Yordi desires the ending balance in Raw Materials Inventory to be 60% of the next​ month's direct materials needed for production. Desired ending balance for February is $48,500. Prepare Yordi​'s direct materials...

  • Beridze Manufacturing expects to produce 2,200 units in January and 3,500 units in February. Beridze budgets...

    Beridze Manufacturing expects to produce 2,200 units in January and 3,500 units in February. Beridze budgets $45 per unit for direct materials. The balance in the Raw Materials Inventory account (all direct materials) on January 1 is $38,150. Beridze desires the ending balance in Raw Materials Inventory to be 20% of the next month's direct materials needed for production. Desired ending balance for February is $51,500. What is the cost of budgeted purchases of direct materials needed for January? $...

  • Prepare a production budget and a direct manufacturing labor cost budget for PetersonPeterson Company by month...

    Prepare a production budget and a direct manufacturing labor cost budget for PetersonPeterson Company by month and for the first quarter of 20182018. You may combine both budgets in one schedule. The direct manufacturing labor cost budget should include​ labor-hours and show the details for each labor cost category. Start the schedule by preparing the production budget and calculating the total hours of direct manufacturing labor time needed for the three months in the​ quarter, then calculate the values for...

  • Thunder Creek Company expects sales of 18,000 units in January 2018, 24,000 units in February, 30,000...

    Thunder Creek Company expects sales of 18,000 units in January 2018, 24,000 units in February, 30,000 units in March, 34,000 in April, and 36,000 in May. The sales price is $34 per unit. Prepare a sales budget 2018 Budget #1: Sales Budget Feb Q1 Total Аpril Jan Mar May Budgeted units to be sold Sales price per unit Total Sales Thunder Creek wants to finish each month with 20 % of next month's sales in units. Prepare a production budget....

  • Yogi Company expects to produce 2,080 units in January that will require 10,400 hours of direct...

    Yogi Company expects to produce 2,080 units in January that will require 10,400 hours of direct labor and 2,210 units in February that will require 11,050 hours of direct labor. Yogi budgets $9 per unit for variable manufacturing​ overhead; $1,900 per month for​ depreciation; and $75,320 per month for other fixed manufacturing overhead costs. Prepare Yogi​'s manufacturing overhead budget for January and February​, including the predetermined overhead allocation rate using direct labor hours as the allocation base. ​(Abbreviations used: VOH​...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT