I need a detailed solution to this.
Solution:
Solution 1) Calculation of overheads to be applied to the job if Traditional Costing using Direct Labour Hours as cost Driver were used.
Overheads to be applied to the job
= (Labour Hours for the Job/ Total Labour Hours) x Total Overhead $
= (25 / 4,000) x $200,000 = $1,250
Therefore, overheads to be applied to the job if Traditional Costing using Direct Labour Hours as cost Driver is $1,250
Solution 2) Calculation of Total Manufacturing Cost for the Job
using Direct Labour Hours as cost Driver.
$ |
|
Direct Labour Cost |
375.00 |
Direct Material |
2,700.00 |
Overheads applied to the Job |
1,250.00 |
Total Manufacturing Cost |
4,325.00 |
Therefore, Total Manufacturing cost of the job if Traditional Costing using Direct Labour Hours as cost Driver is $4,325
Solution 3) Calculation of overheads to be applied to the job using Activity Based Costing
Calculation of Overhead Cost under different heads
Activity |
Proportion of Overheads Cost % |
Cost $ = Proportion of Overheads Cost % / 100 x Total Overhead Cost |
Material Delivery and Handling |
30 |
60,000.00 |
Inspections |
25 |
50,000.00 |
Supervisions |
20 |
40,000.00 |
Purchasing |
25 |
50,000.00 |
2,00,000.00 |
Calculation of Rate per Cost Driver
Activity |
Cost $ |
Cost Driver |
Number of Cost Drivers (Standard + Custom Made) |
Rate Per Cost Driver = Cost $ / Number of Cost Drivers |
Material Delivery and Handling |
60,000.00 |
Number of Deliveries |
300 Deliveries |
$200.00 per Delivery |
Inspections |
50,000.00 |
Number of Inspections |
1000 Inspections |
$50.00 per Inspection |
Supervisions |
40,000.00 |
Hours of Supervisor Time |
4000 Supervisor Time Hours |
$10.00 per Supervisor Time Hour |
Purchasing |
50,000.00 |
Number of Purchase Orders |
2000 Purchase Orders |
$25.00 per Purchase Order |
2,00,000.00 |
Calculation of overheads to be applied to the job
Activity |
Cost Driver |
Number of Cost Drivers for the Job |
Rate Per Cost Driver |
Overhead Cost $ = Number of Cost Drivers for the Job x Rate Per Cost Driver |
Material Delivery and Handling |
Number of Deliveries |
3 Deliveries |
200.00 |
600.00 |
Inspections |
Number of Inspections |
5 Inspections |
50.00 |
250.00 |
Supervisions |
Hours of Supervisor Time |
5 Supervisor Hours |
10.00 |
50.00 |
Purchasing |
Number of Purchase Orders |
3 Purchase Orders |
25.00 |
75.00 |
975.00 |
Therefore, overheads to be applied to the job as per Activity Based Costing is $975
Solution 4) Calculation of Total Manufacturing Cost for the Job using Activity Based Costing
$ |
|
Direct Labour Cost |
375.00 |
Direct Material |
2,700.00 |
Overheads applied to the Job |
975.00 |
Total Manufacturing Cost |
4,050.00 |
Total Manufacturing Cost for the Job using Activity Based Costing is $4,050
Solution 5)
Cost as per Traditional Allocation $ |
Cost as per Activity Based Costing $ |
|
Direct Labour Cost |
375.00 |
375.00 |
Direct Material |
2,700.00 |
2,700.00 |
Overheads applied to the Job |
1,250.00 |
975.00 |
Total Manufacturing Cost |
4,325.00 |
4,050.00 |
On comparing the 2 allocation methods, we see that there has been an over absorption of overheads to the job by $275.
I need a detailed solution to this. Neal Construction manufactures and installs standard and custom-made cabinetlry for...
Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory overhead activities—production setup, procurement, quality control, and materials management. An activity analysis of the overhead revealed the following estimated activity costs and activity bases for these activities: Activity Activity Cost Activity Base Production setup $ 67,500 Number of setups Procurement 126,000 Number of purchase orders (PO) Quality control 156,000 Number of inspections Materials management 147,000 Number of components Total $496,500 The activity-base...
Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory overhead activities-production setup, procurement, quality control, and materials management. An activity analysis of the overhead revealed the following estimated activity costs and activity bases for these activities: Activity Activity Cost Production setup Procurement $ 58,500 136,500 182,000 200,000 Activity Base Number of setups Number of purchase orders (PO) Number of inspections Number of components Quality control Materials management Total $577,000 The activity-base...
Please show calculations 7 6 Leatherback Inc. manufactures two types of handbags-Standard and Custom-and applies manufacturing overhead to all units using machine hours. Production information follows. Standard Custom Totals 8 Anticipated volume (units) 58,500 31,200 89,700 9 Direct-material cost per unit 46 $ 69 115 10 Direct-labor cost per unit 111 11 12 The controller, who is studying the use of activity-based costing, has determined that the firm's overhead can be identified with three activities: manufacturing setups, machine processing, and...
Please include all details on this sheet. Formulas must be used. Wilkins Corporation manufactures two types of handbags—Standard and Custom—and applies manufacturing overhead to all units using machine hours. Production information follows. Standard Custom Anticipated volume (units) 58,500 31,200 Direct-material cost per unit $ 46 $ 69 Direct-labor cost per unit 51 60 The controller, who is studying the use of activity-based costing, has determined that the firm’s overhead can be identified with three activities: manufacturing setups, machine processing, and...
Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company's operations. Direct labor costs Machine hours Setup hours Standard $50,000 1,500 90 Custom $100,000 1,200 390...
Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company's operations. Standard Custom Direct labor costs Machine hours Setup hours $50,000 $100,000 1,200 1,500 120 360...
please help and show work Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company's operations. Direct labor costs Machine hours Setup hours Standard $50,000 1,200...
please help and show work Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company's operations. Direct labor costs Machine hours Setup hours Standard $50,000 1,200...
Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company's operations. Standard Custom Direct labor costs $50,000 $100,000 Machine hours 1,500 1,200 Setup hours 90 420...
Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company’s operations. Standard Custom Direct labor costs $50,000 $100,000 Machine hours 1,200 1,200 Setup hours 90 420...