Question

Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of t...

Calculating Activity-Based Costing Overhead Rates
Assume that manufacturing overhead for Glassman Company consisted of the following activities and costs:

Setup (1,000 setup hours) $160,000
Production scheduling (400 batches) 76,000
Production engineering (60 change orders) 120,000
Supervision (2,000 direct labor hours) 56,000
Machine maintenance (12,000 machine hours) 84,000
Total activity costs $496,000

The following additional data were provided for Job 845

Direct materials costs $11,000
Direct labor cost (5 Milling direct labor hours;
35 Finishing direct labor hours) $5,000
Setup hours 5 hours
Production scheduling 1 batch
Machine hours used (25 Milling machine hours;
5 Finishing machine hours) 30 hours
Production engineering 3 change orders

a. Calculate the cost per unit of activity driver for each activity cost category.

Setup

Answer

Mark 0.00 out of 1.00

per setup hour
Production scheduling cost

Answer

Mark 0.00 out of 1.00

per batch
Production engineering cost

Answer

Mark 0.00 out of 1.00

per change
Supervision cost Answer

Mark 0.00 out of 1.00

per direct labor hour
Machine operating cost

Answer

Mark 0.00 out of 1.00

per machine hour

b. Calculate the cost of Job 845 using ABC to assign the overhead costs.

Job 845
Direct materials cost Answer

Mark 0.00 out of 1.00

Direct labor cost Answer

Mark 0.00 out of 1.00

Manufacturing overhead costs:
Setup costs Answer

Mark 0.00 out of 1.00

Production scheduling Answer

Mark 0.00 out of 1.00

Production engineering Answer

Mark 0.00 out of 1.00

Supervision Answer

Mark 0.00 out of 1.00

Machine operations Answer

Mark 0.00 out of 1.00

Total cost Answer

Mark 0.00 out of 1.00

c. Calculate the cost of Job 845 using a company-wide overhead rate based on machine hours.

First, compute company-wide overhead rate using machine hours (Note: Information needed for this computation can be found in the table below in part d.)
Round rate to two decimal places.
$Answer

Mark 0.00 out of 1.00

per machine hour

Next, use rounded overhead rate calculated above for calculations below. Round cost answers to the nearest whole number, when needed.

Job 845
Direct materials cost Answer

Mark 0.00 out of 1.00

Direct labor cost Answer

Mark 0.00 out of 1.00

Manufacturing overhead cost: Answer

Mark 0.00 out of 1.00

Total cost Answer

Mark 0.00 out of 1.00

d. Calculate the cost of Job 845 using a machine hour departmental overhead rate for the Milling Department and a direct labor hour overhead rate for the Finishing Department.

Milling Department manufacturing overhead $360,000
Finishing Department manufacturing overhead $136,000
Machine hours used
Milling Department 10,000 hours
Finishing Department 2,000 hours
Labor hours used
Milling Department 1,000 hours
Finishing Department 1,000 hours

Round rates to two decimal places, if needed.
$Answer

Mark 0.00 out of 1.00

per Milling Dept. machine hour
$Answer

Mark 0.00 out of 1.00

per Finishing Dept. direct labor hour

Use rounded overhead rates calculated above for calculations below. Round cost answers to the nearest whole number, when needed.

Job 845
Direct materials cost Answer

Mark 0.00 out of 1.00

Direct labor cost Answer

Mark 0.00 out of 1.00

Manufacturing overhead costs:
Milling Department Answer

Mark 0.00 out of 1.00

Finishing Department Answer

Mark 0.00 out of 1.00

Total cost Answer

Mark 0.00 out of 1.00

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer to Question a:

Question a Calculation of activity rates Activity Calculation Cost Activity Cost Drivers Activity rate Per 160,000 1,000 setu

Answer to Question b:

Question b Job 845 $ Direct Material 11,000 5,000 $ Direct Labor $ Setups 800 ($160 X 5) $ Calculation Production Scheduling

Answer to Question c:

Question c Calculation of Overhead Rate Total Overheads/Machine Hours Calculation of Overhead Rate $496,000/12,000 Calculatio

Answer to Question d:

Question d Milling Department: Calculation of Overhead Rate for Milling Department Total Overheads of Milling Department/Mach

Add a comment
Know the answer?
Add Answer to:
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of t...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of the following...

    Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of the following activities and costs: Setup (1,000 setup hours) $288,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 180,000 Supervision (2,000 direct labor hours) 56,000 Machine maintenance (12,000 machine hours) 168,000 Total activity costs $752,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours; 35 Finishing direct labor hours) $1,000 Setup hours...

  • Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...

    Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 150,000 Supervision (2,000 direct labor hours) 46,000 Machine maintenance (12,000 machine hours) 60,000 Total activity costs $434,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...

  • Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of the following...

    Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of the following activities and costs: Setup (1,000 setup hours) $ 146,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 90,000 Supervision (2,000 direct labor hours) 56,000 Machine maintenance (12,000 machine hours) 96,000 Total activity costs $ 448,000 The following additional data were provided for Job 845: Direct material costs $ 8,000 Direct labor cost (5 Milling direct labor hours; 35 Finishing direct labor hours)...

  • Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of the following...

    Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of the following activities and costs: Setup (1,000 setup hours) $ 146,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 90,000 Supervision (2,000 direct labor hours) 56,000 Machine maintenance (12,000 machine hours) 96,000 Total activity costs $ 448,000 The following additional data were provided for Job 845: Direct material costs $ 8,000 Direct labor cost (5 Milling direct labor hours; 35 Finishing direct labor hours)...

  • Calculating Manufacturing Overhead Rates Windsor Company, accumulated the following data for 2017: Milling Department manufacturing overhead...

    Calculating Manufacturing Overhead Rates Windsor Company, accumulated the following data for 2017: Milling Department manufacturing overhead Finishing Department manufacturing overhead 76,800 Machine hours used S187,200 9,000 hours Milling Department Finishing Department 2,000 hours Labor hours used Milling Department 1,000 hours 1,000 hours Finishing Department Required a. Calculate the plantwide manufacturing overhead rate using machine hours as the allocation base $60 x per machine hour b. Calculate the plantwide manufacturing overhead rate using direct labor hours as the lcaion base x...

  • Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing...

    Traditional Product Costing Versus Activity-Based Costing Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $192,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $39,000 Setup hours 1,500 Materials handling 9,000 Number of moves 300 Assembly 120,000 Assembly hours 12,000 Maintenance 24,000 Maintenance hours 1,200 Total $192,000 Total direct labor hours used during the month were 8,000....

  • Traditional Product Costing Versus Activity-Based Costing High Country Outfitters, Inc., makes backpacks for large sporting goods...

    Traditional Product Costing Versus Activity-Based Costing High Country Outfitters, Inc., makes backpacks for large sporting goods chains that are sold under the customers' store brand names. The accounting department has identified the following overhead costs and cost drivers for next year: Overhead Item Expected Costs Cost Driver Maximum Quantity Setup costs $1,216,800 Number of setups 7,200 Ordering costs 312,000 Number of orders 60,000 Maintenance 1,200,000 Number of machine hours 80,000 Power 120,000 Number of kilowatt hours 600,000 Total predicted direct...

  • Activity-Based Costing, Lean Operations, and the Cost of Quality Use department overhead rates to allocate manufacturing...

    Activity-Based Costing, Lean Operations, and the Cost of Quality Use department overhead rates to allocate manufacturing overhead Offbraugh Furniture uses department overhead rates (rather than a plantwide overhead rate) to allocate its manufacturing overhead to jobs. The company's two production departments have the following departmental overhead rates: Cutting Department: Finishing Department: 12 per machine hour 17 per direct labour hour Assume for Job 392 that direct labour is paid at a rate of $25 per hour and the job used...

  • 4-31 Job costing, accounting for manufacturing overhead, budgeted rates. The Fasano Company uses a job-costing system...

    4-31 Job costing, accounting for manufacturing overhead, budgeted rates. The Fasano Company uses a job-costing system at its Dover, Delaware, plant. The plant has a machining department and a finishing department. Fasano uses normal costing with two direct-cost categories (direct materials and direct manu. facturing labor) and two manufacturing overhead cost pools (the machining department with machine. hours as the allocation base, and the finishing department with direct manufacturing labor costs as the allocation base). The 2011 budget for the...

  • departmental overhead rates​ (rather than a plantwide overhead​ rate) to allocate its manufacturing overhead to jobs....

    departmental overhead rates​ (rather than a plantwide overhead​ rate) to allocate its manufacturing overhead to jobs. The​ company's two production departments have the following departmental overhead​ rates: Cutting​ Department: $ 8$8 per machine hour Finishing​ Department: $ 12$12 per direct labor hour Job 112112 used the following direct labor hours and machine hours in the two manufacturing​ departments: LOADING... ​(Click the icon to view the resources used for Job 112​.) Cutting Finishing JOB 112 Department Department Direct Labor Hours. ....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT