Stage 2 ABC for Manufacturing:
Reassigning Costs to Cost Objectives
Regal Products has developed the following activity cost
information for its manufacturing activities:
Activity |
Activity cost |
Machine setup |
$60.00 per batch |
Movement |
15.00 per batch move |
0.10 per pound |
|
Drilling |
5.00 per hole |
Welding |
2.00 per inch |
Shaping |
25.00 per hour |
Assembly |
19.00 per hour |
Inspection |
2.00 per unit |
Filling an order for a batch of 50 fireplace inserts (each insert weighing 150 pounds) required the following:
Determine the activity cost of converting the raw materials into
50 fireplace inserts.
$Answer
Activity |
Activity cost (a) |
Activity Require for 50 Fireplace (b) | Allocated Activity Cost (AXB) |
Machine setup | $60.00 per batch | 1 Batch | $60.00 |
Movement | |||
Batch | 15.00 per batch move | 3 Move | $45.00 |
Weight | 0.10 per pound | =50UnitX 150 Pund X 3 Move | $2,250.00 |
Drilling | 5.00 per hole | 5 Hole X 50 Unit | $1,250.00 |
Welding | 2.00 per inch | 50 Inch X 50 Unit | $5,000.00 |
Shaping | 25.00 per hour | 0.5 HourX 50 Unit | $625.00 |
Assembly | 19.00 per hour | 1 Hour X 50 Unit | $950.00 |
Inspection | 2.00 per unit | 2 SetX 50 Unit | $200.00 |
Total | $10,380.00 |
Stage 2 ABC for Manufacturing: Reassigning Costs to Cost Objectives Regal Products has developed the following...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following activity cost information for its manufacturing activities: Activity Activity Cost per batch Movement 20.00 per batch 0.10 per pound 3.00 per hole 8.00 per inch Machine setup $70.00 Drilling Welding Shaping 29.00 per hour Assembly 18.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts that weighed 150 pounds each required the following: Three batch moves ....
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following activity cost information for its manufacturing activities: Activity Activity Cost Machine setup $60.00 per batch Movement 15.00 per batch 0.10 per pound Drilling 3.00 per hole Welding 4.00 per inch Shaping 25.00 per hour Assembly 18.00 per hour Inspection 2.00 per unit . Filling an order for a batch of 50 fireplace inserts that weighed 100 pounds each required the following: . Four batch...
Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2016 for the given activity cost pools Fabrication Department Finishing Department Cost Driver Maintenance Materials handling Machine setups Inspections $35,000 30,000 70,000 $25,000 Machine hours 15,000 Material moves 5,000 Machine setups 25,000 Inspection hours $135,000 $70,000 The following activity predictions were also made for the year: Machine hours Material moves Machine setups Inspection hours Fabrication Department Finishing Department 5,000 1,500 50 1,000 10,000 3,000 700 It...
Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2016 for the given activity cost pools Fabrication Department Finishing Department Cost Driver Maintenance Materials handling Machine setups Inspections $65,000 30,000 70,000 $55,000 Machine hours 15,000 Material moves 5,000 Machine setups 25,000 Inspection hours 165,000 $100,000 The following activity predictions were also made for the year Machine hours Material moves Machine setups Inspection hours Fabrication Department Finishing Department 5,000 1,500 50 1,000 10,000 3,000 700 It...
Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2016 for the given activity cost pools: Maintenance Materials handling Machine setups Inspections Fabrication Department Finishing Department Cost Driver $35,000 $25,000 Machine hours 30,000 15,000 Material moves 70,000 5,000 Machine setups 25,000 Inspection hours $135,000 $70,000 The following activity predictions were also made for the year: Machine hours Material moves Machine setups Inspection hours Fabrication Department Finishing Department 10,000 5,000 3,000 1,500 700 1,000 50 It...
Anderson Company has the following departmental manufacturing structure for one of its products: 7.5 minutes 15 minutes Wait time = 15 min. Move and wait time = 18 min. Molding Welding Move and wait time = 22.5 min. 12 minutes 7 minutes Move and wait time = 19.5 min. Polishing Assembly After some study, the production manager of Anderson recommended the following revised cellular manufacturing approach: 15 minutes 7.5 minutes Welding Molding Polishing Assembly 12 minutes 10.5 minutes Required: 1....
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Finishing Department Department Fabrication Cost Driver $ 30,000 15,000 Machine hours Maintenance Materials handling 22,500 Material moves 45,000 Machine 7,500 Machine setups 105,000 Inspections 37,500 Inspection hours $180,000 $82,500 Total The following activity predictions were also made for the year: Finishing Fabrication Department Department Machine hours 5,000 2,500 Material moves 1,500 750 Machine setups 350 25 Inspection hours 500...
Activity-Based Costing Steampunk Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Finishing Dement Department Center Maintenance 550.000 10000 Machine hours handing 90,000 45.000 Materal moves Machine 200.000 15.000 chines Inspections M The following activity predictions were also made for the years Fabrication Finishing Department Department Machine hours Material moves Machine Setups 350 5.00 It is assumed that the cost per unit of activity for a given activity does not...
P5-4A. Stage
Two ABC for Manufacturing Merlot Company has determined
its activity cost pools and cost drivers to be the following:
Cost
Pools
Setup……………………………………………………………………………………………………………………$59,500
Materials
handling……………………………………………………………………………………………….$16,000
Machine
operation……………………………………………………………………………………………….$300,000
Packing…………………………………………………………………………………………………………………$60,000
Total indirect
Manufacturing costs………………………………………………………………………..$435,500
Cost
drivers
Setups……………………………………………………………………………………………………………………..$350
Materials
moves………………………………………………………………………………………………………$640
Machine
hours…………………………………………………………………………………………………………$20,000
Packing
orders…………………………………………………………………………………………………………$1,000
One product made by
Merlot, metal casements, used the following activities during the
period to produce 500 unit:
Setups……………………………………………………………………………………………………………………..20
Materials
moves……………………………………………………………………………………………………….80
Machine
hours…………………………………………………………………………………………………………1,900
Packing
orders………………………………………………………………………………………………………….150
Required
Calculate the cost per unit of activity for each activity cost
pool...
The Homer Corporation produces two products, and reports the following production and cost information for the most recent accounting period Product A Product B Number of units produced 15,e80 units 2,500 units Direct labor $25 per direct labor hour (DLH) Direct materials cost 0.50 DLH per unit $ 2 per unit 2.00 DLH per unit $ 30 per unit Activity Driver Overhead costs Machine setup Quality inspections Total Total Cost $ 3,000. etups Product A 5 setups Product B 20...