Franklin Electric Generators is considering a project with the following data. What is the project's MIRR? Enter your answer as a decimal with four places of precision (i.e. 0.1234).
WACC = 10%
Year: | 0 | 1 | 2 | 3 | 4 |
Cash Flow: | -$1,000 | $350 | $370 | $250 | $420 |
We use the formula:
A=P(1+r/100)^n
where
A=future value
P=present value
r=rate of interest
n=time period.
Future value of inflows=350*(1.1)^3+370*(1.1)^2+250*(1.1)+420
=1608.55
MIRR=[Future value of inflows/Present value of outflows]^(1/time period)-1
=[1608.55/1000]^(1/4)-1
=0.1262(Approx).
Franklin Electric Generators is considering a project with the following data. What is the project's MIRR?...
Sammy's Gas Generators (SGG) is considering a project with the following data. What is the project's IRR? Enter your answer as a decimal with four places of precision (i.e. 0.1234). WACC = 10% Year: 0 1 2 3 4 Cash Flow: -$1,000 $350 $370 $250 $420
Hindelang Inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your answer is 0.12345 or 12.345% then enter as 12.35 in the answer box. WACC: 11% Year: 0 1 2 3 4 Cash flows: -$875 $350 $375 $400 $425
1. Frye Foods is considering a project that has the following cash flow data. What is the project's IRR? Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your answer is 0.12345 or 12.345% then enter as 12.35 in the answer box. Year: 0 1 2 3 4 5 Cash flows: -$1,150 $325 $325 $325 $325 $325 2.Van Auken Inc. is considering a project that has the following cash flows:...
Edelman Electric Systems is considering a project that has the following cash flow and WACC data. What is the project’s MIRR? Note that a project’s projected MIRR can be less than the WACC (and even negative), in which case it will be rejected. WACC: 10.00% Year: 0 1 2 3 Cash flows: –$800 $350 $350 $350 a. 11.82% b. 9.58% c. 10.64% d. 13.14%
Tuttle Enterprises is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that if a project's projected NPV is negative, it should be rejected. WACC = 14.50% Year:01234Cash Flow:$1,000$350$350$350$350
Ehrmann Data Systems is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Note that a project's projected MIRR can be less than the WACC (and even negative), in which case it will be rejected.WACC: 9.00% Year 0 1 2 3Cash flows -$1,000 $450 S450 $450 14.53% 17.29% 13.70% 13.84% 13.28%
IRR, MIRR, NVP a. Project M costs $45,000, its expected cash inflows are $8,000 per year for 8 years, and its WACC is 9%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places.___% b. A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $883.36 $250 $5 $15 Project L -$1,000 $5 $240 $380 $807.41 The company's WACC...
Gamma Enterprises, Inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your answer is 0.12345 or 12.345% then enter as 12.35 in the answer box. WACC: 13% Year: 0 1 2 3 4 Cash flows: -$1,100 $300 $320 $340 $550
Gamma Enterprises, Inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your answer is 0.12345 or 12.345% then enter as 12.35 in the answer box. WACC: 11% Year: 0 1 2 3 4 Cash flows: -$1,100 $300 $320 $340 $550
Ellmann Systems is considering a project that has the following cash flow and WACC data. The WACC is 7%. The CF0 = -$1,000, CF1 = $331, CF2 = $473, and CF3 = $597. What is the project's NPV? Computer Consultants Inc. is considering a project that has the following cash flow and WACC data. The WACC is 10.2%. The CF0 = -$1,000, CF1 = $450, CF2 = $450, and CF3 = $450. What is the project's MIRR? Garner Inc. is...