Question 15:
A firm is considering a project that has the following cash flow and cost of capital (r) data.
r = |
11.00% |
|||
Year |
0 |
1 |
2 |
3 |
Cash flows |
−$800 |
$350 |
$350 |
$350 |
What is the project's MIRR?
Solution :
MIRR = ( Future value of cash inflow / present value of cash outlay )^ (1/year) - 1
Future value of cash flow = 350 *(1+11%)^2 + 350 *(1+11%)^1 + 350 * ( 1+11%) ^0
Future value of cash flow = 350 *1.11^2 + 350 * 1.11 + 350
Future value of cash flow = 350 *1.21 + 350 *1.1 + 350
Future value of cash flow = 423.5 + 385 + 350 = 1158.5
MIRR = ( 1158.5/800) ^(1/3) - 1 = 1.448125^(1/3) - 1 = 1.13136 -1 = 13.14%
MIRR = 13.14 %
Question 15: A firm is considering a project that has the following cash flow and cost...
Nichols Inc. is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's IRR can be less than the cost of capital or negative, in both cases it will be rejected. Year 0 1 2 3 4 5 Cash flows −$1,250 $325 $325 $325 $325 $325 a. 10.92% b. 9.43% c. 11.47% d. 10.40% e. 9.91% Westwood Painting Co. is considering a project that has the following cash flow and cost...
Question 12: Feng Inc. is considering a project that has the following cash flow and cost of capital (r) data. r: 10.00% Year 0 1 2 3 Cash flows −$1,050 $450 $460 $470 What is the project's NPV?
Edelman Electric Systems is considering a project that has the following cash flow and WACC data. What is the project’s MIRR? Note that a project’s projected MIRR can be less than the WACC (and even negative), in which case it will be rejected. WACC: 10.00% Year: 0 1 2 3 Cash flows: –$800 $350 $350 $350 a. 11.82% b. 9.58% c. 10.64% d. 13.14%
Billy Bob Baseballs is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r: 12.00% Year 0 1 2 3 Cash flows −$1,000 $126 $126 $126 (Answer in $s to the nearest penny, xxx.xx, with no $ sign or comma needed, but use a minus sign - , if needed.)
Question 13: A firm is considering a project that has the following cash flow. Year 0 1 2 3 4 5 Cash flows −$9,500 $2,000 $2,025 $2,050 $2,075 $2,100 What is the project's IRR?
QUESTION 19 Malhotra Inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Note that a project's projected MIRR can be less than the WACC (and even negative), in which case it will be rejected. WACC 10.0096 Year0 Cash flows $800 3 $340 $300 $320 $360 a. 17.4296 b. 19.3396 O c. 16.20% d. 21.42% e. 17.07%
Malholtra Inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR? WACC: 10.00% Year 0 1 2 3 4 Cash flows $750 $300 $320 $340 $360
1) Last month, Standard Systems analyzed the project whose cash flows are shown below. However, before the decision to accept or reject the project took place, the Federal Reserve changed interest rates and therefore the firm's cost of capital (r). The Fed's action did not affect the forecasted cash flows. By how much did the change in the r affect the project's forecasted NPV? Note that a project's expected NPV can be negative, in which case it should be rejected....
Ehrmann Data Systems is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Note that a project's projected MIRR can be less than the WACC (and even negative), in which case it will be rejected.WACC: 9.00% Year 0 1 2 3Cash flows -$1,000 $450 S450 $450 14.53% 17.29% 13.70% 13.84% 13.28%
Hindelang Inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your answer is 0.12345 or 12.345% then enter as 12.35 in the answer box. WACC: 11% Year: 0 1 2 3 4 Cash flows: -$875 $350 $375 $400 $425