Question

Problem 12-21 WACC and NPV [LO 4] Hankins, Inc., is considering a project that will result...

Problem 12-21 WACC and NPV [LO 4]

Hankins, Inc., is considering a project that will result in initial aftertax cash savings of $5.5 million at the end of the first year, and these savings will grow at a rate of 3 percent per year indefinitely. The firm has a target debt–equity ratio of .54, a cost of equity of 13.4 percent, and an aftertax cost of debt of 6.8 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective approach and applies an adjustment factor of +3 percent to the cost of capital for such risky projects.

Calculate the WACC. (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
  
WACC             %

What is the maximum cost the company would be willing to pay for this project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
  
Present value            $

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Particulars Equity Debt weight 0.649 0.351 cost 13.40% 6.80% weighted cost 0.087 0.024 11.09% WACC Cost of capital = WACC + 3

Add a comment
Know the answer?
Add Answer to:
Problem 12-21 WACC and NPV [LO 4] Hankins, Inc., is considering a project that will result...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Hankins, Inc., is considering a project that will result in initial aftertax cash savings of $7...

    Hankins, Inc., is considering a project that will result in initial aftertax cash savings of $7 million at the end of the first year, and these savings will grow at a rate of 3 percent per year indefinitely. The firm has a target debt-equity ratio of .69, a cost of equity of 13.4 percent, and an aftertax cost of debt of 6.4 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective...

  • Hankins, Inc., is considering a project that will result in initial aftertax cash savings of $5.7...

    Hankins, Inc., is considering a project that will result in initial aftertax cash savings of $5.7 million at the end of the first year, and these savings will grow at a rate of 3 percent per year indefinitely. The firm has a target debt-equity ratio of .56, a cost of equity of 13.1 percent, and an aftertax cost of debt of 5 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective...

  • Problem 13-16 WACC and NPV Och, Inc., is considering a project that will result in initial...

    Problem 13-16 WACC and NPV Och, Inc., is considering a project that will result in initial aftertax cash savings of $1.85 million at the end of the first year, and these savings will grow at a rate of 3 percent per year indefinitely. The company has a target debt-equity ratio of .85, a cost of equity of 12.5 percent, and an aftertax cost of debt of 5.3 percent. The cost-saving proposal is somewhat riskier than the usual projects the firm...

  • Och, Inc., is considering a project that will result in initial aftertax cash savings of $1.86...

    Och, Inc., is considering a project that will result in initial aftertax cash savings of $1.86 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely. The company has a target debt-equity ratio of .8, a cost of equity of 12.6 percent, and an aftertax cost of debt of 5.4 percent. The cost-saving proposal is somewhat riskier than the usual projects the firm undertakes; management uses the subjective...

  • Sommer, Inc., is considering a project that will result in initial aftertax cash savings of $1.86...

    Sommer, Inc., is considering a project that will result in initial aftertax cash savings of $1.86 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely. The firm has a target debt-equity ratio of .80, a cost of equity of 12.6 percent, and an aftertax cost of debt of 5.4 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective...

  • Sommer, Inc., is considering a project that will result in initial aftertax cash savings of $1.78...

    Sommer, Inc., is considering a project that will result in initial aftertax cash savings of $1.78 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely. The firm has a target debt-equity ratio of .80, a cost of equity of 11.8 percent, and an aftertax cost of debt of 4.6 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective...

  • Hi, I am not able to find a correct answer for the following question. Can someone...

    Hi, I am not able to find a correct answer for the following question. Can someone please solve it? Thanks! Hankins, Inc., is considering a project that will result in initial aftertax cash savings of $6.1 million at the end of the first year, and these savings will grow at a rate of 3 percent per year indefinitely. The firm has a target debt–equity ratio of .60, a cost of equity of 13 percent, and an aftertax cost of debt...

  • Sommer, Inc., is considering a project that will result in initial aftertax cash savings of $1.84...

    Sommer, Inc., is considering a project that will result in initial aftertax cash savings of $1.84 million at the end of the first year, and these savings will grow at a rate of 1 percent per year indefinitely. The firm has a target debt-equity ratio of .75, a cost of equity of 12.4 percent, and an aftertax cost of debt of 5.2 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective...

  • Sommer, Inc., is considering a project that will result in initial aftertax cash savings of $1.83...

    Sommer, Inc., is considering a project that will result in initial aftertax cash savings of $1.83 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely. The firm has a target debt-equity ratio of.80, a cost of equity of 12.3 percent, and an aftertax cost of debt of 5.1 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective approach...

  • Sommer, Inc., is considering a project that will result in initial aftertax cash savings of $1.75...

    Sommer, Inc., is considering a project that will result in initial aftertax cash savings of $1.75 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely. The firm has a target debt-equity ratio of 80, a cost of equity of 11.5 percent, and an aftertax cost of debt of 4.3 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT