CALCULATION OF CURRENT LEVEL OF PRODUCTION: | |||
Total Capacity of production (6,000 Units X 12 Month) | 72000 | Units | |
Production is done at 70% efficiency (72,000 X 70%) | 50400 | Units | |
CALCULATION OF CURRENT LEVEL OF OPERATION | |||
Production and sales (50,400 Units X 26) = | £ 13,10,400 | ||
Less: Production Cost: | |||
Direct Material (50,400Units X 8) | £ 4,03,200 | ||
Direct Labor ( 50,400 Units X 6) | £ 3,02,400 | ||
Variable Overhead (50,400 Units X 5) | £ 2,52,000 | ||
Gross Profit | £ 3,52,800 | ||
Less : Fixed Cost | £ 2,00,000 | ||
Net Income | £ 1,52,800 | ||
Answer = Option D = 152,800 | |||
Select one : A. £304,000 B. £404,000 C. £352,800 D. £152,800 €8 As the accounting expert...
Which product should be recommended to be discontinued, 1,2,3 or 4? As the accounting expert for a local firm of management consultants, you have been left with three scenarios to resolve for different clients. Scenario 2: Bromwich Ltd produces four products. The budgeted results suggest the following for next year Product Sales 80,000 76,000 35,000 19,000 Variable costs 62,000 28,000 37,500 11,000 Fixed costs 21,000 18,000 8,000 2,000 Profit/(Loss) (3,000) 30,000 (10,500) 6,000 The Managing Director is wondering whether or...
Advise on the ticket price needed to achieve this level of profit. A. £21,00 B. £6,15 C. 27,15 D. £23.90 As the accounting expert for a local firm of management consultants, you have been left with three scenarios to resolve for different clients. Scenario 3: Albion Ltd are currently organising their annual Christmas dance. The local hotel has a capacity of 400 in their main function suite, exactly equal to the number of employees expected at the event. Costs quoted...
SECTION A (40 marks): Answer ALL Questions in this section. QUESTION ONE a) Aseda Ltd incurred the following cost in its manufacturing operations GH¢ Cost of material purchase 20,000 Import duties 400 Trade discount @10% of purchase cost Cash discount 500 Irrecoverable taxes 1,000 Salary of factory plant operator 2,500 Direct labour 5,000 Salary of factory supervisor 4,000 Cost of expected production losses 800 Administrative overhead (Note) 16,000 Cost of storage of raw material for further processing 2,000 Marketing cost...
How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...
I need Summary of this Paper i dont need long summary i need What methodology they used , what is the purpose of this paper and some conclusions and contributes of this paper. I need this for my Finishing Project so i need this ASAP please ( IN 1-2-3 HOURS PLEASE !!!) Budgetary Policy and Economic Growth Errol D'Souza The share of capital expenditures in government expenditures has been slipping and the tax reforms have not yet improved the income...