Super Systems Ltd. manufactures a number of computer hardware products. The following variable cost standards have been set for one of their products. Particulars Standard Price/rate Direct materials $10 per pound Direct labor ? Variable manufacturing overhead $5.375 per hour Total standard variable cost to manufacture the product is $75 per product. During February, 850 direct labor hours were worked and 600 units of the product were manufactured. Each unit of product required one unit of raw material. The actual cost per unit manufactured during February was $0.30 higher than the standard cost. For the month of February, the standard cost of production for direct labor was $14,000 and for variable manufacturing overhead was $4,300. Actual variable manufacturing overhead was $4,340. Actual costs incurred for materials used were $24,000. The material quantity usage variance was an unfavorable $700. Fixed overhead per direct labor is $3.5 (assuming normal capacity of 900 labor hours). Actual fixed overhead incurred was $3,500 (use labor hours as cost driver for overhead costs). There was no stock of materials in the beginning of the February however, at the end of the month there were 100 units of materials. Question 1 - Calculate the total standard cost of materials used for actual production during February "$41,300 " "$18,300 " "$21,000 " "$26,700 "
Standard labor hours =Standard variable manufacturing overhead / Variable manufacturing overhead = 4300 / 5.375 = 800 hours
Standard direct labor rate per hour = 14000 / 800 = 17.5
Standard hours per unit = 800/ 600 = 1.33
Standard direct labor cost = 17.5 * 1.33 =23.28
Standard variable manufacturing cost = 1.33 *5.375 = 7.2
Standard direct material cost = 75 - 23.28 -7.2 = 44.5 i.e . 4.45 per pound
Standard cost of materials used for actual production = 4.45*10*600 = 26700
Option $ 26700
Super Systems Ltd. manufactures a number of computer hardware products. The following variable cost standards have...
Super Systems Ltd. manufactures a number of computer hardware products. The following variable cost standards have been set for one of their products. Particulars Standard Price/rate Direct materials $10 per pound Direct labor ? Variable manufacturing overhead $5.375 per hour Total standard variable cost to manufacture the product is $75 per product. During February, 850 direct labor hours were worked and 600 units of the product were manufactured. Each unit of product required one unit of raw material. The actual...
2.
Puvo, Inc., manufactures a single product in which variable manufacturing overhead is assigned on the basis of standard direct labor-hours. The company uses a standard cost system and has established the following standards for one unit of product: Standard Price or Standard Standard Quantity 6.70 pounds Rate Cost $ 3.35 Direct materials $ .50 per pound $42.50 per hour $ 9.40 per hour Direct labor 0.40 hours $17.00 $ 3.76 Variable manufacturing overhead 0.40 hours During March, the following...
2.
Irving Corporation makes a product with the following standards for direct labor and variable overhead: Standard Quantity or Hours 0.20 hours 0.20 hours Standard Price or Standard Cost Per Rate Unit $30.00 per hour $6.00 $ 6.60 per hour $1.32 Direct labor Variable overhead In November the company's budgeted production was 6,900 units, but the actual production was 6,700 units. The company used 1,520 direct labor-hours to produce this output. The actual variable overhead cost was $9,424. The company...
Xavier Company produces a single product. Variable manufacturing overhead is applied to products on the basis of direct labor-hours. The standard costs for one unit of product are as follows: Direct material: 6 ounces at $0.50 per ounce . . . . . . . . . . . . . . . . . . $3 Direct labor: 1.8 hours at $10 per hour . . . . . . . . . . . . . . ....
Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit Direct materials: Standard: 1.80 feet at $1.20 per foot $ 2.16 Actual: 1.75 feet at $1.60 per foot $ 2.80 Direct labor: ...
Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit $ 2.88 $ 3.50 16.20 Direct materials: Standard: 1.80 feet at $1.60 per foot Actual: 1.75 feet at $2.00 per foot Direct labor: Standard: 0.90 hours at $18.00 per hour Actual: 0.95 hours at $17.40 per hour Variable overhead: Standard: 0.90 hours at $6.00 per hour Actual:...
Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit $ 3.60 $ 3.85 18.00 Direct materials: Standard: 1.80 feet at $2.00 per foot Actual: 1.75 feet at $2.20 per foot Direct labor: Standard: 0.90 hours at $20.00 per hour Actual: 0.95 hours at $19.40 per hour Variable overhead: Standard: 0.90 hours at $6.40 per hour Actual:...
Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit Direct materials: Standard: 1.80 feet at $1.60 per foot $ 2.88 Actual: 1.75 feet at $2.00 per foot $ 3.50 Direct labor: Standard: 0.90 hours at $18.00 per hour 16.20 Actual: 0.95 hours at $17.40 per hour 16.53 Variable overhead: Standard: 0.90 hours at $6.00 per hour...
Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit $ 5.04 $ 5.25 15.30 Direct materials: Standard: 1.80 feet at $2.80 per foot Actual: 1.75 feet at $3.00 per foot Direct labor: Standard: 0.90 hours at $17.00 per hour Actual: 0.95 hours at $16.40 per hour Variable overhead: Standard: 0.90 hours at $7.40 per hour Actual:...
Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit $ 6.46 $ 7.03 19.00 Direct materials: Standard: 1.90 feet at $3.40 per foot Actual: 1.85 feet at $3.80 per foot Direct labor: Standard: 0.95 hours at $20.00 per hour Actual: 1.00 hours at $19.50 per hour Variable overhead: Standard: 0.95 hours at $7.00 per hour Actual:...