Power | Maintenance | HR | Machining | Painting | Total allocated | |
Operating costs | 700000 | 450000 | 369000 | 850000 | 370000 | |
Allocation of Power department costs | -700000 | |||||
(Total base = 62450 kwh) | 16813 | 7286 | 394556 | 281345 | 700000 | |
0 | 466813 | 376286 | 1244556 | 651345 | ||
Allocation of Maintenance department costs | ||||||
(Total base = 39300 Sq mt) | -466813 | 9503 | 356346 | 100965 | 466813 | |
0 | 0 | 385788 | 1600901 | 752310 | ||
Allocation of HR cost | ||||||
(Total base = 115 employees) | -385788 | 318695 | 67094 | 385788 | ||
Total operating cost after allocation | 0 | 0 | 0 | 1919596 | 819403 | |
Answer: Option [d] $1,919,597 | ||||||
[Difference in calculation statement amount of $1 is due to approximation differences) |
5. Al-Bishi Corp. is preparing its year-end reporting and wants to allocate the operating cost of...
5-40
Chapter 5 Job-Order Costing Professional Examination Problem 5-40 (Appendix 5B) Departmental Costing and Cost Allocation-Corinth Ltd. Corinth Ltd. consists of four departments: personnel and purching, which are service depart. ments; and machining and painting, which are production departments. Budgeted data for the year consisted of the following: Item Personnel Purchasing Machining Painting Overhead costs $40,000 $35,000 $128,000 S48,000 Number of employees 138 Machine hours 23,500 Direct labour costs $32,000 $147,000 Purchase requisitions 2,650 450 10 25 29 Required: 1....
The Sendai Co., Ltd., of Japan has budgeted costs in its various departments as follows for the coming year Factory Administration Custodial Services Personnel Maintenance Machining overhead Assembly-overhead Total cost $ 533,800 102,568 68,774 151,718 1,851,536 761,704 $3,470, 100 The company allocates service department costs to other departments in the order listed below. Department Factory Administration Custodial Services Personnel Maintenance Machining Assembly Square Total Teet of Direct Number of Labor Space Labor- Machine Employees Hours Occupied Hours Hours - 6,500...
Problem 4B-6 Step-Down Method versus Direct Method; Predetermined Overhead Rates [LO4-10, LO4-11] The Sendai Co., Ltd., of Japan has budgeted costsin its various departments as follows for the coming уear: Factory Administration Custodial Services 825,470 108,831 Personnel 28,970 60,569 633,098 865,282 $2,522,220 Maintenance Machining-overhead Assembly-overhead Total cost The company allocates service department coststo other departments in the order listed below. Square Feet of Total Direct Number of Labor Labor- Machine- Space Hours Occupied Employees Department Factory Administration Custodial Services Hours...
The Sendai Co., Ltd., of Japan has budgeted costs in its various departments as follows for the coming year: Factory Administration $ 350,700 Custodial Services 122,425 Personnel 56,830 Maintenance 116,045 Machining—overhead 1,210,800 Assembly—overhead 1,074,200 Total cost $ 2,931,000 The company allocates service department costs to other departments in the order listed below. Department Number of Employees Total Labor- Hours Square Feet of Space Occupied Direct Labor- Hours Machine- Hours Factory Administration 26 — 7,600 — — Custodial Services 13 9,300...
The Sendai Co. Ltd. of Japan has budgeted costs in its various departments as follows for the coming year Factory Administration Custodial Services Personnel Haintenance Machining-overhead Assembly-overhead Total cost 819,840 98,337 26,356 170, SSS 1,126,484 618, 226 12,859,600 The company allocates service department costs to other departments in the order listed below. Department Factory Administration Custodial Services Personnel Maintenance Machining Assembly Square Total Feet of direct Number of Labor Space Labor Machine Employees Hours Occupied Hours Hours 5,500 11 15,900...
The Sendai Co., Ltd., of Japan has budgeted costs in its various departments as follows for the coming year: Factory Administration Custodial Services $ 640,680 103,274 Personnel 31,056 148,590 1,391,860 510,140 Maintenance Machining-overhead Assembly-overhead Total cost $2,825,600 The company allocates service department costs to other departments in the order listed below. Square Feet of Direct Total Number of Labor- Space Labor- Machine- Bours Department Employees Hours Occupied Hours 32 13 Factory Administration Custodial Services Personnel 5,700 3,600 8,100 52,900 14,100...
The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments such as Quality Control and Maintenance to the Machining and Assembly production departments. To aid them in this discussion, the controller has provided the following information: Quality Control Maintenance Machining Assembly Total Budgeted overhead costs before allocation $350,000 $200,000 $400,000 $300,000 $1,250,000 Budgeted Machine-hours - - 50,000 - 50,000 Budgeted Direct manufacturing labor-hours - - - 25,000 25,000 Budgeted units of service: - Quality...
The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments such as Quality Control and Maintenance to the Machining and Assembly production departments. To aid them in this discussion, the controller has provided the following information: Quality Control Maintenance Machining Assembly Total Budgeted overhead costs before allocation $350,000 $200,000 $400,000 $300,000 $1,250,000 Budgeted Machine-hours - - 50,000 - 50,000 Budgeted Direct manufacturing labor-hours - - - 25,000 25,000 Budgeted units of service: - Quality...
Problem 4B-6 Step-Down Method versus Direct Method; Predetermined Overhead Rates [LO4-10, LO4-11] The Sendai Co., Ltd., of Japan has budgeted costsin its various departments as follows for the coming уear: Factory Administration Custodial Services 825,470 108,831 Personnel 28,970 60,569 633,098 865,282 $2,522,220 Maintenance Machining-overhead Assembly-overhead Total cost The company allocates service department coststo other departments in the order listed below. Square Feet of Total Direct Number of Labor Labor- Machine- Space Hours Occupied Employees Department Factory Administration Custodial Services Hours...
The Sendal Co., Ltd., of Japan has budgeted costs in its various departments as follows for the coming year, Factory Administration Custodial Services Personnel Maintenance Machining-overhead Assembly-overhead Total cost $1,614,315 143,440 46,502 129,983 1,313,880 232,480 $2,880,680 The company allocates service department costs to other departments in the order listed below. Department Factory Administration Custodial Services Personnel Maintenance Machining Assembly Square Total Feet of Direct Number of Labor Space Labor- Machine- Employees Hours Occupied Hours Hours 25 9,600 15,400 3,500 12,400...