Question

At the beginning of the year, Learer Companys manager estimated total direct labor cost assuming 40 persons working an avera

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
ans 1 Predetermined overhead rate
estimated overhead rate/Estimted direct labor cost
1300000/(2500*40*20) 0.650
ans 1b
Total overhead cost apllied
Job Direct labor cost applied rate Overhead cost applied
201 $605,000 0.65 $393,250
202 564000 0.65 $366,600
203 299000 0.65 $194,350
204 717000 0.65 $466,050
205 315000 0.65 $204,750
206 18000 0.65 $11,700
$2,518,000 Total $1,636,700
ans 1c
Underapplied
Actual $1,665,000
Less: Applied $1,636,700
Underapplied $28,300
Factory Overhead
Actual $1,665,000 Applied $1,636,700
End bal $28,300
31-Dec
Cost of good sold $28,300
Factory overhead $28,300
If any doubt please comment. If satisfied rate
Add a comment
Know the answer?
Add Answer to:
At the beginning of the year, Learer Company's manager estimated total direct labor cost assuming 40...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • At the beginning of the year, Learer Company's manager estimated total direct labor cost assuming 35...

    At the beginning of the year, Learer Company's manager estimated total direct labor cost assuming 35 persons working an average of 3,000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for the year. Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 335,200 165,000 156,000 104,000 84,000 413,000...

  • At the beginning of the year, Learer Company’s manager estimated total direct labor cost assuming 40...

    At the beginning of the year, Learer Company’s manager estimated total direct labor cost assuming 40 persons working an average of 2,000 hours each at an average wage rate of $40 per hour. The manager also estimated the following manufacturing overhead costs for the year. Indirect labor $ 324,200 Factory supervision 355,000 Rent on factory building 145,000 Factory utilities 93,000 Factory insurance expired 73,000 Depreciation—Factory equipment 750,000 Repairs expense—Factory equipment 65,000 Factory supplies used 73,800 Miscellaneous production costs 41,000 Total...

  • In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons...

    In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons working an average of 3,000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for 2017 Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 336,200 276,000 157,000 105,000 85,000 625,000 77,000 85,800...

  • In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons...

    In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons working an average of 3,000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for 2017 Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 336,200 276,000 157,000 105,000 85,000 625,000 77,000 85,800...

  • 1 In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 50...

    1 In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 50 persons working an average of 2,500 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for 2017 Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 333,200 128,000 154,000 102,000 82,000 494,000 74,000...

  • In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 55 persons...

    In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 55 persons working an average of 2.000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for 2017 Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 261,200 156,000 152, eee 1ee, eee se, eee...

  • In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons...

    In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons working an average of 3,000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for 2017 Indirect labor $ 316, 200 Factory supervision 188,800 Rent on factory building 147,000 Factory utilities 95,000 Factory insurance expired 75, eee Depreciation-Factory equipment 521,000 Repairs expense-Factory equipment 67,000 Factory supplies used 75,800 Miscellaneous production costs 43,000 Total...

  • In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 50 persons...

    In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 50 persons working an average of 2,000 hours each at an average wage rate of $25 per hour. The manager also estimated the following manufacturing overhead costs for 2017. Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Factory supplies used Miscellaneous production costs Total estimated overhead costs $ 319,200 240,000 140,000 88,000 68,000 480,000 60,000 68,800...

  • In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons...

    In December 2016, Learer Company's manager estimated next year's total direct labor cost assuming 40 persons working an average of 2,000 hours each at an average wage rate of $30 per hour. The manager also estimated the following manufacturing overhead costs for 2017. Indirect labor Factory supervision Rent on factory building Factory utilities Factory insurance expired Depreciation-Factory equipment Repairs expense-Factory equipment Pactory supplies used Miscellaneous production costs Total estimated overhead coats $ 332,200 243,000 103,000 101,000 81,000 496,000 73,000 81,800...

  • Chap 15 Homework At the beginning of the year Learer Company's manager estimated total direct labor...

    Chap 15 Homework At the beginning of the year Learer Company's manager estimated total direct labor cost assuming 50 persons working an average of 2.500 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for the year 333,200 120.000 144.000 102,000 Suced Indirect labor Factory supervision Rent on factory building Factory utilities Factory Insurance expired Depreciation Factory equipment Repairs expense actory equipment Factory Supplies used Miscellaneous production costs Total...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT