Question

LUCIL Allen FIURI ES5 Your answer is partially correct. The following direct materials and direct labor data pertain to the o
Standard hours used 4,080 hours Standard quantity of materials used 1,880 tons (a) Compute the total, price, and quantity var
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Total materials variance = Actual quantity of materials purchased and used * Actual materials price - Standard quantity of materials used * Standard materials price
Total materials variance = 1,900 * $130 - 1,880 * $133
Total materials variance = $3,040 Favorable

Materials price variance = Actual quantity of materials purchased and used * (Actual materials price - Standard materials price)
Materials price variance = 1,900 * ($130 - $133)
Materials price variance = $5,700 Favorable

Materials quantity variance = Standard materials price * (Actual quantity of materials purchased and used - Standard quantity of materials used)
Materials quantity variance = $133 * (1,900 - 1,880)
Materials quantity variance = $2,660 Unfavorable

Total labor variance = Actual hours incurred and used * Actual labor rate - Standard hours used * Standard labor rate
Total labor variance = 4,000 * $13.00 - 4,080 * $12.50
Total labor variance = $1,000 Unfavorable

Labor price variance = Actual hours incurred and used * (Actual labor rate - Standard labor rate)
Labor price variance = 4,000 * ($13.00 - $12.50)
Labor price variance = $2,000 Unfavorable

Labor quantity variance = Standard labor rate * (Actual hours incurred and used - Standard hours used)
Labor quantity variance = $12.50 * (4,000 - 4,080)
Labor quantity variance = $1,000 Favorable

Add a comment
Know the answer?
Add Answer to:
LUCIL Allen FIURI ES5 Your answer is partially correct. The following direct materials and direct labor...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 23-8 Your answer is partially correct. Try again. The following direct materials and direct labor...

    Exercise 23-8 Your answer is partially correct. Try again. The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate Actual materials price Standard labor rate Standard materials price $13 per hour $220 per ton $12.50 per hour $224 per ton Quantities Actual hours incurred and used Actual quantity of materials purchased and used Standard hours used Standard quantity of materials used 4,200 hours 1,600 tons 4,280...

  • Exercise 11-8 a The following direct materials and direct labor data pertain to the operations of...

    Exercise 11-8 a The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $16 per hour Actual materials price $110 per ton Standard labor rate $15.50 per hour Standard materials price $112 per ton Quantities Actual hours incurred and used 4,500 hours Actual quantity of materials purchased and used 1,100 tons Standard hours used 4,540 hours Standard quantity of materials used 1,085 tons (a) Compute the...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $13 per hour Actual materials price $290 per ton Standard labor rate $12.50 per hour Standard materials price $292 per ton Quantities Actual hours incurred and used 4,200 hours Actual quantity of materials purchased and used 1,000 tons Standard hours used 4,290 hours Standard quantity of materials used 990 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $180 per ton Standard labor rate $14.50 per hour Standard materials price $182 per ton Quantities Actual hours incurred and used 4,700 hours Actual quantity of materials purchased and used 1,900 tons Standard hours used 4,760 hours Standard quantity of materials used 1,890 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $140 per ton Standard labor rate $14.50 per hour Standard materials price $142 per ton Quantities Actual hours incurred and used 3,800 hours Actual quantity of materials purchased and used 1,500 tons Standard hours used 3,850 hours Standard quantity of materials used 1,490 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $15 per hour Actual materials price $140 per ton Standard labor rate $14.50 per hour Standard materials price $142 per ton Quantities Actual hours incurred and used 3,800 hours Actual quantity of materials purchased and used 1,500 tons Standard hours used 3,850 hours Standard quantity of materials used 1,490 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate $12 per hour Actual materials price $190 per ton Standard labor rate $11.50 per hour Standard materials price $193 per ton Quantities Actual hours incurred and used 4,100 hours Actual quantity of materials purchased and used 1,500 tons Standard hours used 4,140 hours Standard quantity of materials used 1,490 tons (a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs $13 per hour Actual labor rate Actual materials price $220 per ton $12.50 per hour Standard labor rate Standard materials price $224 per ton Quantities Actual hours incurred and used 4,200 hours Actual quantity of materials purchased and used 1,600 tons Standard hours used 4,280 hours Standard quantity of materials used 1,580 tons a) Compute the total, price, and...

  • The following direct materials and direct labor data pertain to the operations of Laurel Company for...

    The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Exercise 25-6 The following direct materials and direct labor data pertain to the operations of Laurel Company for the month of August. Costs Actual labor rate Actual materials price Standard labor rate Standard materials price $13 per hour $220 per ton $12.50 per hour $224 per ton Quantities Actual hours incurred and used Actual quantity of materials purchased and used...

  • The tollowing direct materials and direct labor data pertain to the operations of Laurel Company tor...

    The tollowing direct materials and direct labor data pertain to the operations of Laurel Company tor the month of August Costs Actual labor rate Actual materials price Standard labor rate Standard materials price $16 per hour $260 per ton $15.50 per hour $263 per ton uantities Actual hours incurred and used Actual quantity of materials purchased and used Standard hours used Standard quantity of materials used 3,700 hours 1,700 tons 3,780 hours 1,690 tons Compute the total, price, and quantity...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT