The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments such as Quality c
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Under direct method, the service departments cost will be allocated to production departments, without considering the services incurred on other service departments,

Total units served by quality control will be 21000 + 7000 = 28000, and therefore the cost allocated to assembly department will be 350,000 x 7000 ÷ 28000 = 87,500, and

Total units served by maintenance department will be 18000 + 12000 = 30000, therefore cost allocated to assembly department will be 200,000 x 12000 ÷ 30000 = 80,000.

Therefore the answer is 87,500 + 80,000 = 167,500.

Add a comment
Know the answer?
Add Answer to:
The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments...

    The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments such as Quality Control and Maintenance to the Machining and Assembly production departments. To aid them in this discussion, the controller has provided the following information: Quality Control Maintenance Machining Assembly Total Budgeted overhead costs before allocation $350,000 $200,000 $400,000 $300,000 $1,250,000 Budgeted Machine-hours - - 50,000 - 50,000 Budgeted Direct manufacturing labor-hours - - - 25,000 25,000 Budgeted units of service: - Quality...

  • The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments...

    The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments such as Quality Control and Maintenance to the Machining and Assembly production departments. To aid them in this discussion, the controller has provided the following information: Quality Control Maintenance Machining Assembly Total Budgeted overhead costs before allocation $350,000 $200,000 $400,000 $300,000 $1,250,000 Budgeted Machine-hours - - 50,000 - 50,000 Budgeted Direct manufacturing labor-hours - - - 25,000 25,000 Budgeted units of service: - Quality...

  • The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments...

    The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments such as dua ty Control and Maintenance to the Machining and Assembly production departments. To aid them in this discussion, the controller has provided the following information: Quality Control Maintenance Machining Assembly Total Budgeted overhead costs before allocation $350,000 $200,000 $400,000 $300,000 $1,250,000 50,000 50,000 Budgeted Machine-hours Budgeted Direct manufacturing labor hours 25,000 25,000 Budgeted units of service: - Quality Control 7,000 21,000 18,000...

  • The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments...

    The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments such as Quality Control and Maintenance to the Machining and Assembly production departments. To aid them in this discussion, the controller has provided the following information: Quality Maintenance Machining Assembly Total Control Budgeted overhead costs before allocation $350,000 $200,000 $400,000 $300,000 $1,250,000 Budgeted Machine-hours 50,000 50,000 Budgeted Direct manufacturing labor- hours 25,000 25,000 Budgeted units of service: - Quality Control 7 000 21,000 7.000...

  • The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments...

    The managers of Yoyodyne Propulsion Systems are discussing ways to allocate the cost of support departments such as Quality Control and Maintenance to the Machining and Assembly production departments. To aid them in this discussion, the controller has provided the following information: Quality Control Maintenance Machining Assembly Total Budgeted overhead costs before allocation $350,000 $200,000 $400,000 $300,000 $1,250,000 50,000 50,000 Budgeted Machine-hours Budgeted Direct manufacturing labor- hours 25,000 25,000 Budgeted units of service - Quality Control 7,000 7,000 21,000 18,000...

  • The Sendai Co., Ltd., of Japan has budgeted costs in its various departments as follows for...

    The Sendai Co., Ltd., of Japan has budgeted costs in its various departments as follows for the coming year Factory Administration Custodial Services Personnel Maintenance Machining overhead Assembly-overhead Total cost $ 533,800 102,568 68,774 151,718 1,851,536 761,704 $3,470, 100 The company allocates service department costs to other departments in the order listed below. Department Factory Administration Custodial Services Personnel Maintenance Machining Assembly Square Total Teet of Direct Number of Labor Space Labor- Machine Employees Hours Occupied Hours Hours - 6,500...

  • The Wallaby Company has two support departments and two producing departments. Information for each department for...

    The Wallaby Company has two support departments and two producing departments. Information for each department for the year is as follows:                                          Support Departments         Producing    Departments                                                 Administration  Maintenance    Molding     Assembly       Budgeted overhead         $80,000       $120,000              $460,000     $540,000       Direct labor hours                 500          2,000                      25,000       32,000       Square meter occupied         200            300                        2,500      10,000       Machine hours                        —              500                          9,600     14,400 The company does not divide costs into fixed and variable components. Plant administration costs are allocated based on square meter occupied, and factory maintenance costs are allocated based on machine hours. Predetermined overhead rates for the...

  • Requirement 2. Using the direct method, rework requirement 1 Using the direct method, allocate support-department costs....

    Requirement 2. Using the direct method, rework requirement 1 Using the direct method, allocate support-department costs. (Round cost allocations to the nearest whole dollar. Use parentheses or a minus sign when decreasing departments by allocating costs.) Operating Departments Support Departments General Cafeteria Plant Operating Bldg and Storeroom Machining Grounds Personnel Admin. Loss Assembly Costs incurred Allocation of costs: Building and grounds Personnel General plant administration Cafeteria Storeroom Total budgeted costs of operating departments Enter any number in the edit fields...

  • Caro Manufacturing has two production departments, Machining and Assembly, and two service departments, Maintenance and Cafeteria....

    Caro Manufacturing has two production departments, Machining and Assembly, and two service departments, Maintenance and Cafeteria. Direct costs for each department and the proportion of service costs used by the various departments for the month of August follow. Proportion of Services Used by Maintenance Cafeteria Machining Assembly Department Machining Assembly Maintenance Cafeteria Direct Costs $ 95,000 68,400 42,400 34,00 0.2 0.1 0.8 Exercise 11-28 (Algo) Allocating Service Department Costs First to Production Departments and Then to Jobs (LO 11-2) Assume...

  • allocate suspion departments Alcase the cost of the support parents in the underg r o u...

    allocate suspion departments Alcase the cost of the support parents in the underg r o u nd Sorter 0232010011503150 The budget for de 11/20/2019 Data Table Using the browser's print will lead to an undesirable print-out. Use the Print item from the "Question Help" menu to get a better print-out. Direct Square Feet of Manufacturing Number of Floor Space Manufacturing Number of Department Labor-Hours Employees Occupied Labor-Hours Requisitions Building and grounds Personnel General plant administration Cafeteria: operating loss Storeroom 1,500...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT