1. Predetermined overhead rate per direct labor dollar = total manufacturing overhead applied / total direct labor cost
= 151000/166000 = $0.91 per direct labor dollar
Predetermined overhead rate | $0.91 | Per direct labor dollar |
2.
Work in progress at the end of August (see calculation in notes ) | $376050 |
Notes :-
1 Balance in work in progress as on Aug 31 will be calculated as follows :-
Balance WIP as on aug 1 | 128000 |
Direct material used | 122800 |
Direct labor | 166000 |
Manufacturing overhead applied | 151000 |
Total cost on all jobs till the end of aug | $567800 |
(-) cost of following fininshed jobs | |
- job 234 | (71950) |
- job 237 | (32800) |
- job 231 | (60000) |
- job 246 | (27000) |
Total work in progress at the end of August | $376050 |
3. Following is the direct material cost and applied overhead for job 248 :-
Direct material cost (see calculation in note3 below ) | $331165 |
Applied overhead (see calculation in note 2 below ) | $21385 |
Notes :-
Calculation of applied overhead
We know applied overhead rate = $0.91 per direct labor dollar
Direct labor in job 248 = $23500
Thus, applied overhead = 0.91x23500 = $21385.
Thus Thus direct material cost ,= Work in progress - direct labor - applied overhead
= 376050 (from note 1)-23500-21385 = $331165.
Following is partial information for Delamunte Industries for the month of August: Work In Process Balance,...
Following is partial information for Delamunte Industries for the month of August: Work In Process Balance, August 1 $ 134,000 Direct materials used 114,800 Direct labor 163,000 Manufacturing overhead applied (based on direct labor cost) 152,000 Jobs finished during August are summarized here: Job # Cost of Jobs Completed 234 $ 59,950 237 28,800 231 47,000 246 20,000 Required: At the end of August, only one job, Job 248, was still in process. The direct labor cost incurred on Job...
9.09 points Following is partial information for Delamunte Industries for the month of August Balance, August 1 Direct materials used Direct labor Manufacturing overhead applied Process S 41,000 75,000 120,000 90,000 Jobs finished during August are summarized here: of Jobs Job # 234 237 231 246 Completed S 58,000 5,000 74,500 67,500 Required At the end of August, only one job, Job 248, was stl in process. The direct labor cost incurred on Job 248 as of August 31 was...
On August 1, Cairle Company’s work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,700 $2,000 $850 Direct labor 1,900 1,200 900 Applied overhead 1,330 840 630 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72 Job 73 Job 74 Job 75 Job 76 Direct materials $800 $1,235 $3,600 $5,000 $300 $560 $80...
The Work in Process inventory account of a
manufacturing Corporation shows a balance of $18,000 at the end of
an accounting period.
The job cost sheets of the two uncompleted jobs show
charges of $6,000 and $3,000 for materials, and charges of $4,000
and $2,000 for direct labor.
From this information, it appears that the Corporation
is using a predetermined overhead rate, as a percentage of direct
labor costs. Find the percentage.
Question No. 2: What is underapplied overhead and...
The Work-in-Process Inventory account of a manufacturing firm has a balance of $3,400 at the end of an accounting period. The job cost sheets of two uncompleted jobs show charges of $450 and $250 for materials used, and charges of $450 and $750 for direct labor used. Overhead is applied as a percentage of direct labor costs. The predetermined rate is: Multiple Choice 44.1%. 125.0%. 80.0%. 226.7%.
on august 1st, Carole
or Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company's work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 72 Direct materials Job 71 $2,000 1,300 $1,600 1,900 $850 Direct labor 900 Applied overhead 1,425 975 675 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72...
Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company’s work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,500 $2,000 $850 Direct labor 1,900 1,200 900 Applied overhead 1,520 960 720 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72 Job 73 Job 74 Job...
Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company's work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,700 $850 Direct labor 1,900 1,94 $2,000 1,200 960 900 Applied overhead 1,520 720 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72 Job 73 Job 74...
Predetermined Overhead Rate, Application of Overhead to Jobs, Job Cost, Unit Cost On August 1, Cairle Company's work-in-process inventory consisted of three jobs with the following costs: Job Job 70 Job 71 72 Direct materials $1,500 $2,000 $850 Direct labor 1,900 1,400 900 Applied overhead 1,520 1,120 720 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job Job Job Job Job 71 Job 72 Job 73 70...
apter 21 E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost of Goods Sold [LO 2- Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April Jobs A and B were in process at the beginning of April....