Discounted PBP | ||||
Time | Amount | PVf at 7% | PV | Cumulative |
- | (17,606.00) | 1.0000 | (17,606.00) | (17,606.00) |
1.00 | 5,568.00 | 0.9346 | 5,203.74 | (12,402.26) |
2.00 | 5,633.00 | 0.8734 | 4,920.08 | (7,482.18) |
3.00 | 5,924.00 | 0.8163 | 4,835.75 | (2,646.43) |
4.00 | 8,418.00 | 0.7629 | 6,422.05 | 3,775.62 |
PBP = 3 +2646.43/6422.05 | ||||
PBP = 3 + .41 Years | ||||
PBP = 3.41 Years |
Find the Discounted Payback period for the following project. The discount rate is 7% Project X...
Find the Discounted Payback period for the following project. The discount rate is 7% Project X Initial Outlay $8,133 Year 1 $3,458 Year 2 $3,955 Year 3 $5,978 Year 4 $6,367 Round the answer to two decimal places.
Find the Discounted Payback period for the following project. The discount rate is 7% Project X Initial Outlay $8,492 Year 1 $3,682 Year 2 $3,794 Year 3 $5,908 Year 4 $6,928 Round the answer to two decimal places.
Find the Discounted Payback period for the following project. The discount rate is 6% Project X Initial Outlay $8,901 Year 1 $3,673 Year 2 $3,405 Year 3 $5,468 Year 4 $7,129 Round the answer to two decimal places.
Find the Discounted Payback period for the following project. The discount rate is 9% Project X Initial Outlay $8,805 Year 1 $3,984 Year 2 $3,396 Year 3 $5,804 Year 4 $6,488 Round the answer to two decimal places.
Find the Discounted Payback period for the following project. The discount rate is 9% Project X Initial Outlay $8,236 Year 1 $3,283 Year 2 $3,625 Year 3 $5,116 Year 4 $7,409 Round the answer to two decimal places.
Find the Discounted Payback period for the following project. The discount rate is 10% Project X Initial Outlay $17,274 Year 1 $5,000 Year 2 $5,965 Year 3 $5,705 Year 4 $8,743 Round the answer to two decimal places.
Question 4 (1 point) Find the Discounted Payback period for the following project. The discount rate is 9% Project X Initial Outlay $17,174 Year 1 $5,861 Year 2 $5,397 Year 3 $5,918 Year 4 $8,969 Round the answer to two decimal places.
Find the Biscounted Payback period for the following project. The discount rate is 8% Project X Initial Outlay $17,573 Year 1 $5,839 Year 2 $5,721 Year 3 $5,988 Year 4 $8,743 Round the answer to two decimal places.
Discounted payback period) Assuming an appropriate discount rate of 11 percent, what is the discounted payback period on a project with an initial outlay of $100,000 and the following cash flows? Year 1 $30,000 Year 2 $35,000 Year 3 $25,000 Year 4 $25,000 Year 5 $30,000 Year 6 $20,000 The project's discounted payback period is years. (Round to two decimal places.)
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) 0 $(180) 1 100 2 65 3 100 4 110 If the project's appropriate discount rate is 13 percent, what is the project's discounted payback period? The project's discounted payback period is _____ years. (Round to two decimal places.)