Solution 1:

Direct labor hours for Job A-500 = Direct labor cost / $14 per hour = $280 / $14 = 20 hours

Overhead Assigned to Job A-500 = Direct labor hours * $19 per DLH = 20 * $19 = $380

Total manufacturing cost = Direct materials + direct labor + Overhead assigned = $260 + $280 + $380 = $920

Solution 2:

Unit product cost = Total manufacturing costs / units = $920 / 50 = $18.40 per unit

Add a comment
Know the answer?
Add Answer to:
Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Mickley Company’s plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage...

    Mickley Company’s plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $14.00 per hour. The following information pertains to Job A-500: Direct materials $ 260 Direct labor $ 210 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 80 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.)

  • 3 Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor hour and its direct...

    3 Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor hour and its direct labor wage rate is $14.00 per hour. The following information pertains to Job A-500 Direct materials Direct labor $ 260 $ 140 nts Skipped Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) eBook 1. Total manufacturing...

  • Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage...

    Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $12.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor 250 $ 180 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 30 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost 2. Unit product cost Der...

  • Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage...

    Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 230 $ 110 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost 2. Unit product cost...

  • Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage...

    Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 230 $ 110 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) x Answer is complete but not entirely correct....

  • Mickley Company's plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage...

    Mickley Company's plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 231 $ 153 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 40 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost 2. Unit product cost...

  • Mickley Company's plantwide predetermined overhead rate is $22.00 per direct labor-hour and its direct labor wage...

    Mickley Company's plantwide predetermined overhead rate is $22.00 per direct labor-hour and its direct labor wage rate is $14.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 300 $140 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 80 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) Total manufacturing cost 2 Unit product cost per unit

  • Mickley Company's plantwide predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage...

    Mickley Company's plantwide predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $14.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $300 $140 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 80 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost 2. Unit product cost I per...

  • Mickley Company's plantwide predetermined overhead rate is $18.00 per direct labor-hour and its direct labor wage...

    Mickley Company's plantwide predetermined overhead rate is $18.00 per direct labor-hour and its direct labor wage rate is $10.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 260 $ 50 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 80 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total Total manufacturing cost 2. Unit product...

  • Mickley Company's plantwide predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage...

    Mickley Company's plantwide predetermined overhead rate is $23.00 per direct labor-hour and its direct labor wage rate is $13.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 270 $ 260 Required 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.) 1. Total manufacturing cost 2. Unit product cost...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT