QUESTION 3 | B | C | D | E | F | G | H |
month | Sales forecast | regular production | overtime production | ending inventory | carry over to next month | ||
3 | January | 250 | 250 | 0 | 0 | 0 | |
4 | February | 200 | 300 | 0 | 100 | 100 | G3+F4 |
5 | March | 300 | 325 | 25 | 50 | 150 | G4+F5 |
6 | April | 500 | 400 | 25 | -75 | 75 | G5+F6 |
ANSWER | D)75 UNITS | ||||||
QUESTION 4 | |||||||
month | sales forecast | opening stock | production | closing | cumulative closing | ||
13 | january | 525 | 350 | 610 | 435 | 435 | |
14 | february | 600 | 0 | 610 | 10 | 445 | |
15 | March | 650 | 0 | 610 | -40 | 405 | |
16 | april | 750 | 0 | 610 | -140 | 265 | |
17 | May | 875 | 0 | 610 | -265 | 0 | |
18 | total forecast sales | 3400 | SUM(C13:C17) | ||||
19 | number of month | 5 | |||||
20 | opening stock | 350 | (given) | ||||
21 | adjusted production required to meet the demand ( opening stock is sold in the month of January itself) | 3050 | C18-C20 | fifo basis | |||
22 | average adjusted production required per month | 610 | C21/C19 | ||||
ANSWER | a) 610 units pm |
Question 3 What is the ending inventory level for April in the production plan shown in...
Question 13 (3 points) A company has a sales forecast for the following five months as shown in the table. If they have a beginning inventory of 225 units, what amount should be produced under a level plan in order for them to have an ending inventory of zero units at the end of the five month period? Month Forecast 825 600 650 550 475 anua Febru March A) 595 units per month 580 units per month 575 units per...
please show work A company has a sales forecast for the following five months as shown in the table. If they have a beginning inventory of 225 units, what amount should be produced under a level plan in order for them to have an ending inventory of zero units at the end of the five-month period? Month Forecast January 825 February 600 March April May 650 550 475 A. 595 units per month B. 575 units per month C. 580...
I. Describe the differences between level, chase, and mixed production plans. Use the forecast in the table to show the differences by creating a plan of each type. There is no beginning inventory and regular production capacity is 350 units. Overtime costs $10 extra and is limited to 50 units per month. Subcontracting is limited to 100 units per month and costs $15 per unit. Back orders cost $40 per unit and there is a cost of $5 per month...
A. Aggregate Planning Problem 1. AUTO Inc. are in the process of developing an aggregate plan for their latest sports car, model "Sporty-Sprinty". Anticipated sales forecast in A.U. for the next four months is tabulated below: Month Jan Feb Mar April Sales forecast (A.U.) 100 200 300 600 Initial inventory (at the beginning of first month) = 100 A.U. Initial workforce level = 50 Minimum ending inventory required at the end of the plan = 30 A.U. Minimum...
Given the following production plan, compute the monthly production, ending inventory/(backlog) and workforce levels using a level production strategy. Assume that a worker can produce 30 units per month and the beginning inventory in June is 400 units, and the firm desires to have 200 units of inventory at the end of November. Month June Jul Aug Sep Oct Nov Demand 1500 2800 4200 3600 2350 1400 Production Ending Inventory Workforce
Problem 8-8 Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply,...
Required information Rulz Co. provides the following sales forecast for the next four months: Sales (units) April 610 May 690 June 640 July 730 The company wants to end each month with ending finished goods inventory equal to 20% of next month's forecasted a goods inventory on April 1s 122 units. Assume July's budgeted production is 640 units. In addition, each finished unit requires five pounds (lbs.) of raw materials and the company wants to end each month with raw...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for bolts of cloth. The figures are in hundreds of bolts. The department has a normal capacity of 275(00) bolts per month, except for the seventh month, when capacity will be 250(00) bolts. Normal output has a cost of $40 per hundred bolts. Workers can be assigned to other jobs if production is less than normal. The beginning inventory is zero bolts. Month Forecast Total...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...