a) NPV at 8%:-
=PV(rate,nper,pmt)-cost
=-PV(8%,8,2620)-9430
=5626.19
b) NPV at 24%:-
=-PV(24%,8,2620)-9430
=-466.40
c) Discount rate:-
=RATE(8,2620,-9430)
=22.19%
7 A project that provides annual cash flows of $2,620 for eight years costs $9,430 today...
A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. a. At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 24 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to...
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What is the NPV for the project if the required return is 7 percent? (Do not round intermediate calculations. Round your answer to 2 decimal places, e.g., 32.16.) NPV At a required return of 7 percent, should the firm accept this project? O Accept O Reject What is the NPV for the project if the required return is 19 percent? (Negative amount should be indicated...
A project that provides annual cash flows of $2,650 for nine years costs $10,900 today. At a required return of 8 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV At a required return of 24 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...
A project that will provde annual cash flows of $2,750 for nine years costs $9.000 today, a. At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 29 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...
A project that will provde annual cash flows of $2,550 for nine years costs $10,500 today. a. At a required return of 11 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 27 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...
A project that will provde annual cash flows of $3,000 for nine years costs $10,000 today. a. At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 28 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...
A project that will provde annual cash flows of $2,750 for nine years costs $9,000 today. a. At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. At a required return of 29 percent, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...
A) A project that provides annual cash flows of $14369 for eight years costs $77894 today. What is the NPV for the project if the required return is 7 percent? (Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places. (e.g., 32.16)) B) A project that provides annual cash flows of $17545 for eight years costs $75634 today. What is the NPV for the project if the required return is 19 percent? (Negative amount...
A project that provides annual cash flows of $14369 for eight years costs $77894 today. What is the NPV for the project if the required return is 7 percent? (Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places. (e.g., 32.16)) A project that provides annual cash flows of $17545 for eight years costs $75634 today. What is the NPV for the project if the required return is 19 percent? (Negative amount should be...
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What is the NPV for the project if the required return is 7 percent? What is the NPV for the project if the required return is 19 percent? At what discount rate would you be indifferent between accepting the project and rejecting it?