Accountig Cost
1- La compañía H20 proveyó la siguiente información para diciembre del 2019. $57,900 307,400 Work-in-process inventory, 12/31
2-The following cost data for the month of May were taken from the records of the Terrence Manufacturing Company: $1,000 500
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1a) Total manufacturing cost

direct material used (250800+1750200-169400) 1831600
Direct labor 1004300
Manufacturing overhead 2693400
Total manufacturing cost 5529300

1b) Total cost of work in process = 101000+5529300 = 5630300

1c) Cost of goods manufactured = 5630300-57900 = 5572400

1d) Cost of goods sold = 307400+5572400-511000 = 5368800

1e) Prime cost = 1831600+1004300 = 2835900

1f) Conversion cost = 1004300+2693400 = 3697700

2) Total manufacturing cost

Depreciation on factory equipment 1000
Wages of production workers 28000
Raw material used 47000
Factory rent 2000
Factory insurance 500
Material handling 1500
Total manufacturing cost 80000
Add a comment
Know the answer?
Add Answer to:
Accountig Cost 1- La compañía H20 proveyó la siguiente información para diciembre del 2019. $57,900 307,400...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cost of direct materials used in production Direct labor Work in process inventory, October 1 Work...

    Cost of direct materials used in production Direct labor Work in process inventory, October 1 Work in process inventory, October 31 Total factory overhead $1,323,600 1,680,000 455,300 378,100 3,544,200 Determine Fuller Manufacturing's cost of goods manufactured for the month ended October 31. Fuller Manufacturing Company Statement of Cost of Goods Manufactured For the Month Ended October 31 Work in process inventory, October 1 Manufacturing costs incurred during October: Cost of direct materials used in production Direct labor Factory overhead Total...

  • 15 Requirements: Prepare the schedule of cost of goods manufactured and cost of goods sold. Data:...

    15 Requirements: Prepare the schedule of cost of goods manufactured and cost of goods sold. Data: Raw Materials Inventory, Jan. 1 $10 Raw Materials Inventory, Dec. 31 Work-in-Process Inventory, Jan. 1 Work-in-Process Inventory, Dec. 31 Finished Goods Inventory, Jan. 1 Finished Goods Inventory, Dec. 31 Raw Materials Purchased, incl. freight 30 Direct Labor 40 Manufacturing (factory) Overhead Schedule of Costs of Goods Manufactured Year Ended December 31, 2018 Beginning Work-in-Process Direct Materials Used: Beginning Raw Materials Inventory Purchased of Raw...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company for the month ended March 31 are as follows: Inventories March 1 March 31 Materials $212,000 $182,320 Work in process 1 44,160 123,980 Finished goods 110,240 122,150 S. Direct labor Materials purchased during March Factory overhead incurred during March: $381,600 407,040 Indirect labor Machinery depreciation Heat, light, and power Supplies Property taxes Miscellaneous costs a. Prepare a cost of goods manufactured statement for March....

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Sandusky Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories January 1 January 31 Materials $196,000 $176,400 Work in process 135,240 121,720 Finished goods 99,960 118,190 Direct labor $352,800 Materials purchased during January 376,320 Factory overhead incurred during January: Indirect labor 37,630 Machinery depreciation 22,740 Heat, light, and power 7,840 Supplies 6,270 Property taxes 5,490 Miscellaneous costs 10,190 a. Prepare a cost of goods...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Sandusky Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories Materials January 1 $191,000 126,060 99,320 January 31 $164,260 108,410 110,050 Work in process Finished goods Direct labor $343,800 366,720 Materials purchased during January Factory overhead incurred during January: Indirect labor Machinery depreciation Heat, light, and power 36,670 22,160 7,640 6,110 5,350 9,930 Supplies Property taxes Miscellaneous costs a. Prepare a cost of goods...

  • Cost of Goods Manufactured for a Manufacturing Company The following information is available for Ethtridge Manufacturing...

    Cost of Goods Manufactured for a Manufacturing Company The following information is available for Ethtridge Manufacturing Company for the month ending July 31: Cost of direct materials used in production $106,500 Direct labor 127,800 Work in process inventory, July 1 47,900 Work in process inventory, July 31 65,000 Total factory overhead 58,600 Determine Ethtridge's cost of goods manufactured for the month ended July 31. Ethtridge Manufacturing Company Statement of Cost of Goods Manufactured For the Month Ended July 31 Work...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Sandusky Manufacturing Company for th...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories January 1 January 31 Materials $171,820 $195,250 134,720 99,580 Work in process Finished goods 118,560 116,840 Direct labor $351,450 374,880 Materials purchased during January Factory overhead incurred during January: Indirect labor 37,490 Machinery depreciation Heat, light, and power 22,650 7,810 Supplies 6,250 Property taxes 5,470 Miscellaneous costs 10,150 a. Prepare a cost of goods...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Johnstone Manufacturing Company for the month ended March 31 are as follows: Inventories March 1 March 31 Materials $165,150 $183,500 122,950 110,650 Work in process Finished goods 93,590 110,650 $330,300 352,320 35,230 Direct labor Materials purchased during March Factory overhead incurred during March: Indirect labor Machinery depreciation Heat, light, and power Supplies Property taxes Miscellaneous costs 21,290 7,340 5,870 5,140 9,540 a. Prepare a cost of goods...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Sandusky Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Sandusky Manufacturing Company for the month ended January 31 are as follows: Inventories Material:s Work in process Finished goods January 1 $180,000 334,600 675,000 January 31 $145,500 290,700 715,000 Direct labor Materials purchased during January Factory overhead incurred during January: $2,260,000 1,375,000 115,000 90,000 55,000 18,500 10,000 33,100 a. Prepare a cost of goods manufactured statement for January. Indirect labor Machinery depreciation Heat, light, and power Supplies...

  • Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Disksan Manufacturing Company...

    Statement of Cost of Goods Manufactured for a Manufacturing Company Cost data for Disksan Manufacturing Company for the month ended January 31 are as follows: Inventories January 31 Materials January 1 $228,000 157,320 116,280 $198,360 136,870 Work in process Finished goods 132,900 $410,400 Direct labor Materials purchased during January Factory overhead incurred during January: 437,760 Indirect labor 43,780 26,450 Machinery depreciation Heat, light, and power 9,120 Supplies 7,300 Property taxes 6,380 Miscellaneous costs 11,860 a. Prepare a cost of goods...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT