Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers.

Annual Overhead Data

Estimated Use of
Cost Drivers per Product

Activity Cost Pools

Cost Drivers

Estimated
Overhead

Estimated Use of Cost
Drivers per Activity

Product
BC113

Product
AD908

Machine setup Setups $26,400 44 26 18
Machining Machine hours 82,790 4,870 1,190 3,680
Packing Orders 34,170 510 170 340

Using the above data, do the following:
Prepare a schedule showing the computations of the activity-based overhead rates per cost driver.

Activity Cost
Pools

Estimated
Overhead

Estimated Use of Cost
Drivers per Activity

Activity-Based
Overhead Rates

Machine setup $

setups $

per setup
Machining

machine hours $

per machine hr.
Packing

orders $

per order
$

LINK TO TEXT

Prepare a schedule assigning each activity’s overhead cost to the two products.

BC113

AD908

Activity Cost
Pools

Estimated Use of Cost
Drivers per Product

Activity-Based
Overhead Rates

Cost
Assigned

Estimated Use of Cost
Drivers per Product

Activity-Based
Overhead Rates

Cost
Assigned

Machine setup

$

$

$

$

Machining

$

$

Packing

$

$

Total assigned costs $

$

LINK TO TEXT

Compute the overhead cost per unit for each product. (Round answers to 2 decimal places, e.g. 12.25.)

BC113

AD908

Overhead cost per unit $

$

Click if you would like to Show Work for this question:

Open Show Work

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Ans. 1 Activity cost pool Estimated overhead (a) Estimated use of cost Activity based overhead
drivers per activity (b) rates   (a / b)
Machine setup $26,400 44 setups $600.00 Per direct labor hour
Machining $82,790 4870 machine hours $17.00 Per test
Packing $34,170 510 orders $67.00 Per machine hour
*Activity based overhead rates =   Estimated overhead / Estimated use of cost drivers per activity
Ans. 2 BC 113 AD 908
Activity cost pool Estimated use of cost Activity based   Cost Estimated use of cost Activity based   Cost
Drivers per product (a) Overhead rates   (b) Assigned (a*b) Drivers per product (a) Overhead rates   (b) Assigned (a*b)
Machine setup 26 $600 $15,600 18 $600 $10,800
Machining 1190 $17 $20,230 3680 $17 $62,560
Packing 170 $67 $11,390 340 $67 $22,780
Total Assigned Cost $47,220 $96,140
*Cost assigned = Estimated use of cost drivers per product * Activity based overhead rates
Ans. 3 *Calculations of Overhead cost per unit :
BC113 AD908
Total Assigned Cost (a) $47,220 $96,140
Estimated production (b) 2000 1000
Overhead cost per unit (a / b) $23.61 $96.14
*Overhead cost per unit = Total assigned cost / Estimated production
Add a comment
Know the answer?
Add Answer to:
Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Prod...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Activity Cost Pools Cost Drivers Estimated Overhead Estimated Use of Cost Drivers per Activity Product BC113 Product AD908 Machine setup...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Activity Cost Pools Machine setup Machining Packing Cost Drivers Setups Machine hours Orders Estimated Overhead $14,800 78,560 27,030 Estimated Use of Cost Drivers per Product Estimated Use...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Overhead $17,500 120,750 28,670 Activity Cost Pools Machine setup Machining Packing 20 Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Drivers...

  •    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units...

       Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Product AD908 Activity Cost Pools Machine setup Machining Packing Estimated Overhead $18,500 106,920 35,640 Cost Drivers Setups Machine hours...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Please solve the questions in the boxes, much appreciated! thank you so much!! Annual Overhead Data Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Drivers per...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Drivers BC113 AD908 per Activity Estimated Overhead Activity Cost Pools Cost Drivers Machine setup...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Product AD908 Activity Cost Pools Machine setup Machining Packing Estimated Overhead $22,000 97,200 30,080 Cost Drivers Setups Machine hours Orders 21 Estimated Use of Cost Drivers per...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each . pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Product AD908 Annual Overhead Data Estimated Activity Cost Pools Cost Drivers Overhead Machine setup Setups $22,000 Machining Machine hours 97,200 Packing Orders 30,080 Estimated Use of Cost Drivers per...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 un...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Annual Overhead Data Estimated Overhead $18,500 106,920 35,640 Drivers per Activity Activity Cost Pools Machine setup Machining...

  • Do It! Review 4-2 a-c Flynn Industries has three activity cost pools and two products. It...

    Do It! Review 4-2 a-c Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Drivers per Activity BC113 Product AD908 44 27 Estimated Overhead...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT