Question

Assume a project has normal cash flows. Given this, you should accept the project Multiple Choice...

Assume a project has normal cash flows. Given this, you should accept the project

Multiple Choice

a) if the total cash inflows exceed the initial cash outflow.

b) if, and only if, the NPV is exactly equal to zero.

c) if the NPV is positive and reject it if the NPV is negative.

d) only if the NPV is equal to the initial cash flow.

e) because it has positive cash flows for every time period after the initial investment

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct option is C.

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
NPV=Present value of inflows-Present value of outflows

Hence if NPV is positive Present value of inflows is greater than Present value of outflows which leads to positive value creation of the firm and hence project must be accepted only in that case.

Add a comment
Know the answer?
Add Answer to:
Assume a project has normal cash flows. Given this, you should accept the project Multiple Choice...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with...

    Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The longer a project's payback period, the more desirable the project is normally considered to be by this criterion. b. One drawback of the payback criterion for evaluating projects is that this method does not properly account for the time value of money. c. If a project's payback is positive, then the project...

  • Apply WACC in NPV. Brawn Blenders has the following incremental cash flow for its new project: Ca...

    Apply WACC in NPV. Brawn Blenders has the following incremental cash flow for its new project: Category To -$4,000,000 T1 T2 тз Investment Operating cash flow $1,500,000 $1,500,000 1,500,000 $250,000 Salvage Should Brawn accept or reject this project at an adjusted WACC of 6.00%, 8.00%, or 10.00%? Should Brawn accept or reject this project at an adjusted WACC of 6.00%? (Select the best response.) OA. The project should be rejected because the NPV is negative. The costs exceed the benefits...

  • Which of the following statements is CORRECT? Assume that the project being considered has normal cash...

    Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Group of answer choices A) If a project's IRR is positive, then its NPV must also be positive. B) A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost. C) If a project's IRR is smaller than the WACC, then its NPV will be positive....

  • Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one...

    Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Lumbering Ox Truckmakers is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $2,500,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $325,000 Year 2 $400,000 Year 3 $500,000 Year 4 $475,000...

  • 1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value...

    1. Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Hungry Whale Electronics is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $3,000,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 Year 2 $325,000 $450,000 $425,000...

  • Making the accept or reject decision Pheasant Pharmaceuticals's decision to accept or reject project Alpha is...

    Making the accept or reject decision Pheasant Pharmaceuticals's decision to accept or reject project Alpha is independent of its decisions on other projects. If the firm follows the NPV method, it should project Alpha. Which of the following statements best explains what it means when a project has an NPV of $0? When a project has an NPV of $0, the project is earning a rate of return less than the project's weighted average cost of capital. It's OK to...

  • Assume a new project requires an initial investment of $6 million dollars, with ensuing cash flows...

    Assume a new project requires an initial investment of $6 million dollars, with ensuing cash flows of $1, $3 and $5 million in years 1, 2 and 3. Assuming the company's WACC is 10%, which of the following statements is true? The firm should accept the project, as the IRR is lower than the WACC. The firm should reject the project, as the IRR is higher than the WACC. The firm should accept the project, as the NPV is positive....

  • Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR...

    Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR Cash Flow......($200).....$850....($700)......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Accept the project because the payback is short b. Accept the project because the NPV is greater than zero c. Reject the project because the IRR is less than the required rate of return d. Reject the project because...

  • Assume a project has normal (conventional) cash flows (i.e., initial cash flow is negative, and all...

    Assume a project has normal (conventional) cash flows (i.e., initial cash flow is negative, and all other cash flows are positive). Which of the following statements is most correct? All else equal, a project's IRR increases as the required rate of return declines. All else equal, a project's IRR increases as the required rate of return increases All else equal, a project's NPV increases as the required rate of return declines. None of the above Question 11 (2 points) Suppose...

  • Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one...

    Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Hungry Whale Electronics is evaluating a proposed capital budgeting project (project Alpha) that will require an initial Investment of $500,000. The project is expected to generate the following net cash flows: Year Year 1 Year 2 Year 3 Year 4 Cash Flow $350,000 475,000 400,000 475,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT