Question

Required information (The following information applies to the questions displayed below.] In 2018, the Westgate Construction(The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution to part 3.

Balance Sheet ( Partial) 2018 2019
Current Assets:
Accounts Receivable $220,000 $816,000
Construction In Progress $3,100,000 $7,900,000
Less: Billings (2,040,000) (6,636,000)
Costs and profit in excess of billings $1,060,000 $1,264,000
Current Liabilities:

Workings :

Accounts receivable in 2018 = Billings during the year - Cash collections during the year

= $ 2,040,000 - $ 1,820,000

= $ 220,000

Accounts receivable in 2019 = Opening balance of accounts receivable in 2019 + Billings during the year - Cash collections during the year

= $ 220,000 + $ 4,596,000 - $ 4,000,000

= $ 816,000

Percentage of work completed in 2018 = (Total Costs incurred till date / Total costs to be incurred including current costs)

= [2,604,000 / (2,604,000 + 5,796,000)]

= ( 2,604,000 / 8,400,000)

= 31%

So, construction in progress will be the amount of work completed as a percentage of contact value,

= 31% x Contract price

= 31% x 10,000,000

= 3,100,000

Percentage of work completed in 2019 = (Total Costs incurred till date / Total costs to be incurred including current costs)

= [(2,604,000+ 4,032,000) / (2,604,000+ 4,032,000 +1,764,000 )]

= ( 6,636,000 / 8,400,000)

= 79%

So, construction in progress will be the amount of work completed as a percentage of contact value,

= 79% x Contract price

= 79% x 10,000,000

= 7,900,000

Solution to Part 4:

2018 2019 2020
Revenue $ 3,100,000 $ 3,630,930 $ 3,269,070
Gross Profit ( Loss) $ 496,000 $( 189,070) $49,070

Workings:

2018 2019 2020
Contract Price $ 10,000,000 $10,000,000 $10,000,000
Actual Costs to date $ 2,604,000 $ 6,424,000 $ 9,644,000
Estimated costs to complete $ 5,796,000 $ 3,120,000 0
Total estimated Costs $ 8,400,000 $ 9,544,000 $ 9,644,000
Estimated Gross Profit ( loss) $ 1,600,000 $ 456,000 $ 356,000
( Actual in 2020)

Revenue Recognition: Actual costs to date / Total estimates costs

In 2018 = $ 2,604,000 / 8,400,000 = 31% = 31% x 10,000,000 = $ 3,100,000

In 2019 = $ 6,424,000 / $ 9,544,000 = 67.3093% =( 67.3093 % x 10,000,000 - $ 3,100,000 )= $ 3,630,930

In 2020 = $ 10,000,000 - ( 3,100,000 + 3,630,930)

= $ 3,269,070

Gross Profit (loss) recognition;

In 2018 = revenue realized in 2018 - Total costs incurred in 2018

= $ 3,100,000 - $ 2,604,000

= $ 496,000

In 2019 = revenue realized in 2019 - Total costs incurred in 2019

= 3,630,930 - $ 3,820,000

= $( 189,070)

In 2020 = Total gross profit recognized on project – Gross profit recognized in 2019 – Gross profit recognized in 2018

= $ 356,000 - (189,070) - 496,000

= 49,070

Add a comment
Know the answer?
Add Answer to:
Required information (The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered intoo a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $4,032,000 1,764,000 4,596,000 4,000,000 $2,604,000 5,796,000 2,040,000 1,820,000 $1,940,400 3,364,000 4,180,000...

  • ! Required information [The following information applies to the questions displayed below.] In 2018, the Westgate...

    ! Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,596,000 4,000,000 3,364,000...

  • Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000 Westgate recognizes revenue over time according to percentage of completion....

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Constr...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000...

  • Required Information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required Information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,604,000 5,796,000 2,040,000 1, 820, 000 2022 $4,032,000 1,764,000 4,596,000 4,000,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT